Question




The evaluation team should be made up of: a. representatives from potential contractors. b. several individuals from differen
Companies should decide to outsource a project and prepare decide to outsource a project and prepare a request for proposal w
0 0
Add a comment Improve this question Transcribed image text
Answer #1

5) option B is correct

several individuals from different departments in the organization with various viewpoints and different backgrounds and experiences

Explanation :

The evaluation team is made up of different people from varying fields and background with the basic motive of looking at problems with different angles, perspectives etc.

6) Option c is correct

The project charter helps the team to develop a detailed baseline plan for performing the project.

Explanation :

Project Charter is made up of a team which helps to develop the blueprint for the project to help perform various tasks.

7) option d:

that the sponsor has officially or formally authorised the project.

The approval signature and date in project charter aims to acknowledge the fact that the sponsor or customer has authorised tur project.

8) option c

Outsourcing the project provides sufficient benefits for the project to meet the customer requirements at a realistic price

Outsourcing should be an option only when outsourcing provides benefits to the company and help them meet the customer requirements.

.

9) Option d

outlines the major tasks or work elements to be performed.

The statement of work provides us the idea about the various tasks and operations to be performed which is included in the request for proposal for describing it to the contractors.

.

10) b

Comprehensive and provide sufficient details

Request for proposal should be detailing the customer needs, specifications and requirements through including comprehensive and clear information about the expectations from the project.

.

.

.

Thanks dear student.. Hope I explained well..

Good luck and God bless :)

Please rate if satisfied that will be helpful

Add a comment
Know the answer?
Add Answer to:
The evaluation team should be made up of: a. representatives from potential contractors. b. several individuals...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1 You are project manager in a global project with a team consisting of people from...

    1 You are project manager in a global project with a team consisting of people from various countries. What can you try to prevent misunderstandings due to cross-cultural differences? a Use all communication methods available that are suitable for the team and follow up in writing when communicating verbally. Remember that cultural and individual diversity may help project teams solving unforeseen problems during the course of the project. b When you are about to form a team for your project,...

  • 1 Which statement describes best why you should document assumptions? a Assumptions might prove to be...

    1 Which statement describes best why you should document assumptions? a Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis. b Assumption analysis is a valuable tool and technique to explore the validity of assumptions during risk identification. c Assumptions limit the project management team's options for decision making because they can not be controlled by the team. d In case of schedule or budget overruns, the documentation of assumptions...

  • 7 In the work breakdown structure for a construction project: A. The different levels of detail...

    7 In the work breakdown structure for a construction project: A. The different levels of detail represents the logical hierarchical decomposition of the B. The smallest element in the WBS is the activity C. The project elements at various levels of the WBS relate to the contractor's project organizational structure, which defines the different responsibility levels D. All the above Negotiated cost-plus type of contracts is best used when: A. The risk is high B. No variations are expected C....

  • CASE 17: WATSON’S AMBULATORY EHR TRANSITION Major theme: System acquisition Primary care physicians play a key...

    CASE 17: WATSON’S AMBULATORY EHR TRANSITION Major theme: System acquisition Primary care physicians play a key role in the U.S. health care delivery system. These providers integrate internal and external information with their clinical knowledge to determine the patient’s treatment options. An effective ambulatory electronic health record (EHR) is critical to supply physicians with the information they need to provide quality care and maximize their efficiency. This case involves the decision-making process to replace an inadequate EHR system in a...

  • You are asked to develop a proposal for any product of your choice. Your proposal should...

    You are asked to develop a proposal for any product of your choice. Your proposal should contain the following steps. Project Development Proposal Part #1 A) Specification only Statement of Work & Requirements • Functional Requirements Spec & UI . Budget Team member selections and qualifications Part#2 B) Design only • Interaction Diagrams • Class Diagram, and System Architecture Part#3 C) Product Part #4 D) Conclusions Product Proposal Date: June 2004 Design Organization: Robust Decisions Proposed Product Name: COMFORT BICYCLE...

  • Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong...

    Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong Police (HKP) was responsible for the public safety and internal security of Hong Kong. She came under the umbrella of the Security Bureau of the Government of Hong Kong. It had more than 34,000 employees, of these, over 26,000 were disciplinary staff. This was the largest department within the hierarchy of the Government of Hong Kong. The organization structure of HKP was rather complicated....

  • Cinstruction Law and Ethics the court the right to resolve the dispute? A. B. C. D....

    Cinstruction Law and Ethics the court the right to resolve the dispute? A. B. C. D. Venue Personal jurisdiction Federal question All of the above 49. Which is not a discovery device? A Request for admissions B. Motion for entry upon land C. Production of documents and things D. Live testimony in court 50. Who is usually the best individual with firsthand knowledge of the facts which gave rise to the claim on a job site? Upper management of the...

  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program...

    RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...

  • 1. You work for a large Canadian non-profit organization that holds a big annual conference. The...

    1. You work for a large Canadian non-profit organization that holds a big annual conference. The conference rotates throughout Canada on a yearly basis. A resort and conference company in Hawaii invites you and one other person down for a one-week paid vacation so that you can check out their conference facilities. Should you: Select one: a. Accept the vacation if the majority of the conference attendees are in favour of holding the conference in Hawaii? b. Accept the vacation...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT