Question

Q1 (6 Marks) [CLO 1] Consider two projects: project 2 Annual Interest rate (13%) Project 1 Annual Interest rate (9%) returns


Q1 (6 Marks) [CLO 1] Consider two projects: project 2 Annual Interest rate (13%) Project 1 Annual Interest rate (9%) returns
0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a) Formula for calculating present value PV = Future value * [1+(1+r)n]

For project 1: present value of all future income PV1 = 10,000 * (1+(1+0.09)1] + 50,000 * (1+(1+0.09)2] + 100,000 * (1+(1+0.09)3​​​​​​​] + 135,000 * (1+(1+0.09)4​​​​​​​]

= 9174.31 + 42084 + 77218.35 + 95637.4

= 224,114.06

For project 2 : present value of all future income PV 2 = 15,000 * (1+(1+0.13)1] + 55,000 * (1+(1+0.13)2​​​​​​​] + 115,000 * (1+(1+0.13)3​​​​​​​] + 150,000 * (1+(1+0.13)4​​​​​​​]

= 13274.34 + 43073.07 + 79700.77 + 95064.40

= 23,112.58

(b) Though interest rate is higher in project 2, the net present value of income is higher in this project. Hence Project 2 is profitable

Add a comment
Know the answer?
Add Answer to:
Q1 (6 Marks) [CLO 1] Consider two projects: project 2 Annual Interest rate (13%) Project 1...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 6. The facilities manager was given the following table of potential projects from the planning department....

    6. The facilities manager was given the following table of potential projects from the planning department. The planning engineer has already calculated the net present value of income streams and the net present value of annual expenses for each project. Project A Project B Project C Project D Project E Initial Capital CostNet Present Value of Net Present value of Income stream Annual Expenses -100,000 150,000 25,000 - 150.000 200.000 -25.000 -125,000 135,000 -15,000 -250,000 150,000 50.000 400,000 -350,000 a)...

  • Q3 (6 Marks) [CLO 1] The investors make decision to select appropriate investment project by using...

    Q3 (6 Marks) [CLO 1] The investors make decision to select appropriate investment project by using the concept of present value. If you have 2 investment projects with the same costs as the following: First: Total revenue at the end of every year is $3000 and the interest rate 5%. Second: Total revenue at the end of every year is $3300 and the interest rate 15%. Evaluate the two investment projects through 2 years and decide which project is better...

  • Q3 (6 Marks) [CLO 1] The investors make decision to select appropriate investment project by using...

    Q3 (6 Marks) [CLO 1] The investors make decision to select appropriate investment project by using the concept of present value. If you have 2 investment projects with the same costs as the following: First: Total revenue at the end of every year is $3000 and the interest rate 5%. Second: Total revenue at the end of every year is $3300 and the interest rate 15%. Evaluate the two investment projects through 2 years and decide which project is better...

  • Marks = 30) Year 1 Year 2 evaluating the following two projects. The cost of SARBELLE...

    Marks = 30) Year 1 Year 2 evaluating the following two projects. The cost of SARBELLE LADIES CLUB Company has the chance to open a third brunch. There we toute Project A is AED 550.000, for Project B is AED 350,000. The cost of capital is 10%. Project A Year 3 120,000 Year 4 130,000 Year 5 Project B 145.000 100,000 150.000 165.000 110,000 120,000 140.000 150,000 1) Calculate the net present value (NPV) of the two projects, A and...

  • Q1. Inatech is contemplating two different projects and decides to perform a financial analysis to determine...

    Q1. Inatech is contemplating two different projects and decides to perform a financial analysis to determine which is more financially lucrative. Project A and B have the cash flows as shown and Inatech uses a required rate of return of 10% and an inflation rate of 4%. Compute the payback in years and the net present value for both projects and offer advice as to the best course of action. (4 marks) Yearl A B 0 -$100.000|-$400,000 $20,000 $75,000 2....

  • 3. Consider the information in Table 2. Sports Bulletin Plc. is considering investing in two projects,...

    3. Consider the information in Table 2. Sports Bulletin Plc. is considering investing in two projects, A and B. The initial outlay and annual cash flows are shown in Table 2. Straight-line depreciation method is used. The minimum accounting rate of return is 15%. The discount rate is 10%, and the depreciation rate is 25%. The minimum acceptable pavback period is 3 vears. For each project, the change in net working capital is zero in each vear, Both proiects are...

  • (a) Calculate the IRR, NPV, Annual Percentage Rate and Payback Period for the following projects: PROJECT...

    (a) Calculate the IRR, NPV, Annual Percentage Rate and Payback Period for the following projects: PROJECT A B C D Inicial Investment 1,000,000 2,000,000 2,000,000 1,000,000 (b) Consider the cash flow projection for the next four years. Compare the projects and determine what is the best option for an investor that wants a 10% minimum aceptable rate of return. Years Project A Project B Project C Project D 1 300,000 400,000 400,000 1,000,000 2 400,000 200,000 200,000 1,000,000 3 500,000...

  • Consider four projects, which you expect to generate the following cash flows: Year                      Project A      &nbs

    Consider four projects, which you expect to generate the following cash flows: Year                      Project A        Project B                Project C                Project D 0                         (200,000)               (2,000)                 (200,000)               (200,000) 1                          210,000                 18,000                  100,000                   90,000 2                      (100,000 is for project c & d ONLY)    100,000                100,000 3                                                                                      100,000                115,000 , Your required return on all of the investments is 8%. For each project estimate the Payback Period, Internal Rate...

  • question 2 hello can you help me with these Q1 AND Q2 THAN YOU 2. An account in Building Society A pays 7.4% interest,...

    question 2 hello can you help me with these Q1 AND Q2 THAN YOU 2. An account in Building Society A pays 7.4% interest, compounded quarterly. while another Building Society B pays 7.5% with annual compounding. You have £1,000 to invest. What is the value of your investment in these Societies after three years? Which Society do you prefer? What additional amount would you have to invest in this Society at the start of the fourth year to achieve a...

  • Option #1: Capital Rationing Table with Cash Flows for 5 projects. Project A Project B Project...

    Option #1: Capital Rationing Table with Cash Flows for 5 projects. Project A Project B Project C Project D Project E Initial Investment -$100,000 -$25,000 -$40,000 -$10,000 -$150,000 Year 1 $50,000 $15,000 $20,000 $7,000 $100,000 Year 2 $40,000 $10,000 $15,000 $4,000 $25,000 Year 3 $20,000 $5,000 $5,000 $2,000 $10,000 Year 4 $10,000 $1,000 $5,000 $1,000 $10,000 Year 5 $1,000 $10,000 Year 6 $1,000 $10,000 Calculate the IRR for each of the projects presented. Rank the projects based on their IRR....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT