Final Answer
Particular |
Project A |
Project B |
NPV |
– AED19, 639 (Negative NPV) |
AED 110,725 |
Workings
NPV = Present Value of future cash inflows – Initial Investment
Project A – Calculation of NPV
Initial Investment = AED 550,000
Present Value of future cash inflow
Year |
Cash Flows In AED |
Present value factor @ 10% |
Present Value |
(I) |
(II) |
(III) |
(II) * (III) |
1 |
AED 120,000 |
0.9091 |
AED 109,092.00 |
2 |
AED 130,000 |
0.8264 |
AED 107,432.00 |
3 |
AED 145,000 |
0.7513 |
AED 108,938.50 |
4 |
AED 150,000 |
0.6830 |
AED 102,450.00 |
5 |
AED 165,000 |
0.6209 |
AED 102,448.50 |
Present Value of the future Cash inflows |
AED 530,361.00 |
NPV of project A = AED 530,361 – AED 550,000
= (AED 19,639)
NPV is Negative
i.e. – AED19, 639/-
Project B – Calculation of NPV
Initial Investment = AED 350,000
Present Value of future cash inflow
Year |
Cash Flows In AED |
Present value factor @ 10% |
Present Value |
(I) |
(II) |
(III) |
(II) * (III) |
1 |
AED 100,000 |
0.9091 |
AED 90,910.00 |
2 |
AED 110,000 |
0.8264 |
AED 90,904.00 |
3 |
AED 120,000 |
0.7513 |
AED 90,156.00 |
4 |
AED 140,000 |
0.6830 |
AED 95,620.00 |
5 |
AED 150,000 |
0.6209 |
AED 93,135.00 |
Present Value of the future Cash inflows |
AED 460,725.00 |
NPV of project A = AED 460,725 – AED 350,000
= AED 110,725
NPV is Positive
Answer For Part 2
Explanations for selection
The NPV method provides straightforward criteria for choosing or rejecting investment projects.
Projects with positive NPVs qualify for selection because their benefits, in terms of target returns exceed costs.
Investments yield zero NPV when they have equal benefits and costs.
Negative NPVs, on the other hand, are loss-making investments that must be rejected.
Note:
Calculation of Present value Factor
Discount Factor = 1/ (1+R) N
R = Discount Rate (i.e. = 10%)
N = No of years
E.g. for year 2 Discount Factor = 1/ (1.10)2
= 1/ (1.10) (1.10)
= 0.8264
Marks = 30) Year 1 Year 2 evaluating the following two projects. The cost of SARBELLE...
PART II: (Total Marks - 30) BARBELLE LADIES CLUB Company has the chance to open a third branch. There are two possible locations. The company is evaluating the following two projects. The cost of Project A is AED 550,000, for Project Bis AED 350,000. The cost of capital is 10%. Year 1 Year 2 Year 3 Year 4 Year 5 Project A 120,000 130,000 165,000 145,000 150,000 150,000 Project B 100,000 110,000 120,000 140,000 1) Calculate the net present value...
software company is evaluating the following projects with estimated cash flow (in $): Year (t) Project A Project B Project C 0 -100,000 -100,000 -120,000 1 30,000 30,000 40,000 2 40,000 30,000 40,000 3 40,000 30,000 40,000 4 40,000 30,000 40,000 5 100,000 130,000 120,000 Calculate the net profit, payback period, return on investment (ROI), and net present value (NPV) of all projects. Discount rate= 3.00% a) Show your calculated discount rate and fill in the table. Project A Project...
Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The relevant cash flows for each project are given in the table below. The cost of capital for use in evaluating each of these equally risky projects is 10 percent. initial investment project a project b $350,000 $425,000 year cash inflows (cf) 1 140,000 175,000 2 165,000 150,000 3 190,000 125,000 4 100,000 5 75,000 6 50,000 Which project should be chosen on the basis of...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,266,858 -$1,100,968 1 256,000 319,000 2 318,000 319,000 3 480,000 319,000 4 483,000 319,000 5 773,000 319,000 NPV of project 1 is$ NPV of project 2 is$ IRR of project 1 is % IRR of project 2 is % Crane Corp should accept:
Newton Inc. is evaluating the purchase of a new machine. The cost of the machine is $800,000. The incremental cash flows due to the machine are expected to be as follows: Year 1 $150,000 Year 2 $250,000 Year 3 $350,000 Year 4 $480,000 The cost of capital for Newton, Inc. is 11%. 1. Calculate the NPV and IRR for this project. 2. Should you accept this project? Explain. Mention both NPV and IRR in your explanation. 3. At what costs...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 $1,190,556 -$1,107,928 225,000 315,000 315,000 315,000 405,000 315,000 450,000 315,000 675,000 315,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to O decimal places, e.. 1,525....
, A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects I and II, with cash flows at t0,1 and 2 as follows: Year t Project I Project II - $10,000 +20,000 +10,000 $10,000 +$40,000 Compute each project's NPV for r=0% and r=10%, where r= discount rate or required rate Based on the cash flow patterns for the two projects and the answer to part a), can we Using the analytical formulation of the intersection of...
6) A firm is evaluating three mutually exclusive capital budgeting projects. The net present value of each project is shown below. Given this information, which project() should the firm accept? Project 1 100,000 NPV, S Project 2 10,000 Project 3 - 100,000 a) accept Projects 1 and 2, and reject Project 3 b) accept Projects 1 and 3, and reject Project 2 c) accept Project 3, and reject Projects 1 and 2 d) accept Project 1, and reject Projects 2...
6. The equivalent annual annuity approach - Evaluating projects with unequal lives Aa Aa E Evaluating projects with unequal lives Your company is considering starting a new project in either Spain or Mexico-these projects are mutually exclusive, so your boss has asked you to analyze the projects and then tell her which project will create more value for the company's shareholders. The Spanish project is a six-year project that is expected to produce the following cash flows: The Mexican project...
NPV and IRR. Reece Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Year Project M Project N -$150,000 -$372,000 68,600 159,300 193,200 154,800 2 76,800 71,300 110,400 &se40,500 What is the IRR for each project? a. What is the NPV for each project? b. Which, if either, of the projects should the company accept? C. O-23