Question

The management of Diversified Products Limited (DPL) are investigating whether to increase plant capacity. DPL is...

The management of Diversified Products Limited (DPL) are investigating whether to increase plant capacity. DPL is a manufacturing company that produces an array of products. One of its products, the Pod, has a selling price of $80 per unit. Based on a market survey, which cost $68 500, the marketing director is convinced that sales will increase for the next five years if the company was to increase current capacity. The marketing manager believes that capacity will increase to 35 000 should DPL buy a new plant. If DPL leased a new plant, there would be extra efficiencies and the capacity would increase to 40 000. The marketing manager will earn a bonus of $90 000 at the end of year three if his estimations are correct. The company’s current capacity is 30 000 units per annum. Each unit has a variable cost of $40 and an allocated fixed cost of $15, based on a capacity of 30 000 units per annum. A new plant could be purchased for $850 000. The new plant has an estimated useful life of five years, at the end of which the salvage value is expected to be $230 000. It is estimated that because of technological advances, the new plant will result in increased efficiencies and a reduction in variable costs of $10 per unit. Fixed costs, other than depreciation, are expected to increase by $5 per unit. The wear and tear allowance for the new machine is the same as the accounting depreciation. The lease payments would be $220 000, payable annually in advance for five years. The company’s WACC is 15%, the cost of equity 18% and the debt-to-equity ratio is 0.6. The company’s tax rate is 28% and taxation is paid annually at the end of the year. Required: Advise management in a letter as to whether they should buy or lease the new plant.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Selling Price of the Pod = 80 $

The cost of the market survey is irrespective of which option the company chooses ( buy or lease) and is a sunk cost and hence does not impact the buy or lease decision.

Current Capacity = 30,000 units per annum , Present variable cost per unit = 40 $ , Allocated fixed cost per unit = 15 $

a) Buy Option

Cost of the new plant = 8,50,000 $ , Useful life = 5 years , Salvage Value = 230,000 $

Assuming a straight line depreciation the annual depreciation is = (8,50,000 - 2,30,000)/ 5 =6,20,000/5 = 1,24,000 $

Variable cost with the new plant = 40 - 10 = 30 $ , Allocated fixed cost per unit = 15 + 5 = 20 $

Capacity of the new plant = 35,000 , Addition is capacity = 35000 - 30000 = 5000 units

Incrementa cash flow with the buy option

Reduction in cost for 30,000 units from 55 $ per unit to 50 $ per unit which is a saving of 5 $ per unit

For 30,000 units this is an incremental cash flow of 30,000 * 5 = 1,50,000 $

The profit margin from the additional 5000 units = (80 - 50) * 5000 = 30 * 5000 = 1,50,000 $

Total additional cash flow = 1,50,000 + 1,50,000 - 1,24,000 = 3,00,000 - 1,24,000 = 1,76,000 $

So the company will get this additional cashflow for 5 years if it buys the new plant. The company's wacc is 15% which is the opportunity cost for this.

So using this the NPV of the buy option is = NPV(.15,1,76,000,1,76,000,1,76,000,1,76,000,1,76,000) = 589,979 $

b) Lease option

With lease option the capacity will increase to 40,000 unit which is an increase of 40,000 - 30,000 = 10,000 units

The profit margin from the additional 10,000 units = (80-50) * 10,000 = 30 * 10,000 = 3,00,000 $

The incremental cash flow with lease option = 1,50,000 + 3,00,000 = 4,50,000 $ per year

The NPV of this cash flow is = NPV(.15,4,50,000,4,50,000,4,50,000,4,50,000,4,50,000) = 1,508,469 $

However the company needs to pay lease rental which is a cash outflow.

Annual lease rental = 2,20,000 $ , tax rate = 28%

Since lease rentals are tax deductible the company will pay an effective lease rental of = 2,20,000 * ( 1- .28)

= 1,58,400

Also the lease rentals need to be discounted at company's cost of debt which can be computed from wacc.

.15 = .625 * .18 + .375 ^ Rd * .72

.0375 = .375 * Rd * .72

Rd = 13.88 %

NPV of the lease rental discounted at cost of debt which is paid at the beginning of year is = PV(.1388,5,-158400,0,1) = 621 069 $

This must be deducted the cash inflow as this is the net present value of cash outflow with lease rental

So the NPV of lease option = 1,508,469 - 621069 = 887,400 $

So the lease option still has a higher NPV than the buy option (589,979 $) and so the company should lease the new plant

Add a comment
Know the answer?
Add Answer to:
The management of Diversified Products Limited (DPL) are investigating whether to increase plant capacity. DPL is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • *Separation machine would replace an old work phase and increase this phase’s capacity with 10%. *The...

    *Separation machine would replace an old work phase and increase this phase’s capacity with 10%. *The new equipment would cost 225 000 €, and its lifetime is estimated as 7 years. *The increase in capacity would cause extra revenue of 60 000 € per year. *Based on this information, calculate the payback time. *Is this project justified, if the company’s maximum payback time is 4 years?

  • Hahn Manufacturing purchases a key component of one of its products from a local supplier. The...

    Hahn Manufacturing purchases a key component of one of its products from a local supplier. The current purchase price is $ 1 comma 450 per unit. Efforts to standardize parts succeeded to the point that this same component can now be used in five different products. Annual component usage should increase from 150 to 700 units. Management wonders whether it is time to make the component​ in-house, rather than to continue buying it from the supplier. Fixed costs would increase...

  • ACME manufacturing is considering replacing an existing production line with a new line that has a...

    ACME manufacturing is considering replacing an existing production line with a new line that has a greater output capacity and operates with less labour than the existing line. The existing line, which was purchased several years ago, originally cost $500,000 and currently has a book value of $250,000. The new line would cost $750,000 and would be depreciated on a straight-line basis over a useful life of 5 years. At the end of five years, the new line could be...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

  • Question 9 9) New Plant? Because TrueBeat's capacity is limited to 8,000 units in their current...

    Question 9 9) New Plant? Because TrueBeat's capacity is limited to 8,000 units in their current production facility, management would like to explore the impact of building a new production facility. The company is considering a new production facility and equipment that will decrease their variable expenses by 30% but increase fixed expenses by 50%. TrueBeat still plans to produce and sell the same number of units in Year 4 (base). The new plant will give them a relevant range...

  • The Martin-Beck Company operates a plant in St. Louis with an annual capacity of 30,000 units....

    The Martin-Beck Company operates a plant in St. Louis with an annual capacity of 30,000 units. Product is shipped to regional distribution centers located in Boston, Atlanta, and Houston. Because of an anticipated increase in demand, Martin-Beck plans to increase capacity by constructing a new plant in one or more of the following cities: Detroit, Toledo, Denver, or Kansas City. The estimated annual fixed cost and the annual capacity for the four proposed plants are as follows: Proposed Plant Annual...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A demand for next year ............. 21,000 units selling price per unit ........... $80 direct material cost per unit .... $24 direct labor cost per unit ........ $18 variable overhead cost per unit .. $22 Product B 28,000 units $120 $ 22 $ 50 $ 25 Product C 35,000 units $160...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT