Question

Whats the correct answer?Given the following information, calculate the RMSE. Forecast 12 12 20 12 O a. 50% b.8 Oco O d. 5396

0 0
Add a comment Improve this question Transcribed image text
Answer #1

b. 8

RMSE(Root Mean Square Error) = sqroot{Sum of (Predicted -Actual)2/Number of periods}

= sqroot[{(12-20)2 + (20-12)2}/2]

= sqroot{(64+64)/2}

= sqroot(64)

= 8

Add a comment
Know the answer?
Add Answer to:
Whats the correct answer? Given the following information, calculate the RMSE. Forecast 12 12 20 12...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Calculate the standard deviation of returns of Stock Q, given the following information. State Stock return...

    Calculate the standard deviation of returns of Stock Q, given the following information. State Stock return Probability of state Recession -2% 35% Normal 8% 50% Boom 20% 15% Select one: O a. 7.70% O b. 6.30% c. 5.37% O d. 7.33% o e. 3.66%

  • 9. Forecast the level of Q when P = 5, 10, 20, and 30 given the...

    9. Forecast the level of Q when P = 5, 10, 20, and 30 given the following information: Qx = 100, 88, 76, 65, 54, 47, 35, 28, 21, 18, 10, 8, 6, 3, 1 Px = 1, 4, 8, 12, 15, 18, 22, 26, 29, 31, 35, 40, 44, 48

  • Given the following weekly demand and forecast figures: Week Demand Forecast 1 27 20 2 21...

    Given the following weekly demand and forecast figures: Week Demand Forecast 1 27 20 2 21 25 3 39 35 The mean square error is: a) 5 b) 7 c) 10 d) 17 e) none of the above

  • Which one is the correct answer please be sure Assume the following information to calculate the...

    Which one is the correct answer please be sure Assume the following information to calculate the dollar cost of using a money market hedge to hedge 200,000 pounds of payables due in 180 days. Assume the firm has no excess cash. Assume the spot rate of the pound is $2.02, the 180-day forward rate is $2.00. The British interest rate is 5%, and the US interest rate is 4% over the 180-day period. a $388,210 O b s387.900 O c...

  • Given forecast errors of 8, 10, and 9, what is the mean absolute deviation? O A....

    Given forecast errors of 8, 10, and 9, what is the mean absolute deviation? O A. 2/3 B. 1/3 C.:a. D. O QUESTION 5 Given forecast errors of 3, 6, and 9, what is the mean square error? A. 5 B. 6 c.7 D. 8 We were unable to transcribe this imageTime-series data may exhibit which of the following behaviors? O A. Trend B. Seasonality C. Cycles D. All of the above QUESTION 9 In business, forecasts are the basis...

  • Given the following information about a competitive firm's costs, calculate marginal cost and answer four questions....

    Given the following information about a competitive firm's costs, calculate marginal cost and answer four questions. Instructions: Enter your responses as whole numbers. Indicate negative responses with a (-) negative sign. Marginal Cost Output (units) Total Cost 10 $50 11 52 2 12 56 4 13 62 $ 14 70 15 80 10 $ 16 92 12 106 17 14 $ 18 122 16 $ 19 140 18 a. If the prevailing market price is $12 per unit how much...

  • What is the expected return given the following information? Probability 20% Possible Returns 8% 10% 12%...

    What is the expected return given the following information? Probability 20% Possible Returns 8% 10% 12% 15% 10% 40% 20% 10% 60% 12.2% 12% 12% 18.2% No new data to sav

  • is my solution correct? 3.15. Given the following data, calculate the projected available balance and the...

    is my solution correct? 3.15. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The demand time fence is 2 weeks. 4 2 3 Week 50 50 50 50 Forecast 25 30 65 60 Customer Orders 60 Projected Available Balance MPS 312 3. 15 demand time fence 2 wks lot siza = loo Week Fore cast Customer orders t0 30 Projactd Avaiabe Balano Cbo) 70 (00 LoD

  • 4. Long-Term Forecast Given the following data and the partial calculation in the following table: Note:...

    4. Long-Term Forecast Given the following data and the partial calculation in the following table: Note: A clarification - To assign the AV multiply by 100 not 100% as the text states. The index for each month:                                                                          Leading Indicator                                                    Month       1          2          3          4          5          6          7          8         Diffusion Index                         1          20        50        30        30        50        30        20        30                         2          20        60        30        40        56        40        30        20             AV                    .5         1          ____     1          1          ___      1          0          __________                         3          30        50        35        48        40        40        35        46             AV                    1          ____     1          ____     0          .5         .5         1          __________                         4          38        30        40        55        40        42        35        48                       AV                    .5         0          .5         1          ____     1          .5         1          __________                         5          45        40        30        64        40        42        45        35 AV                    1          ____     0          1          ____     .5         1          0          __________ 6          52        46        30        34        44        50        52        42             AV                    1          ___      .5         0          1          1          1          1          ___________ Calculate the diffusion index for each month starting from month 2 by filling in the blank spaces. You do not have to show every step of your calculations....

  • correct answer? What information can be obtained from the Figure below? 14 12 10 pH 8...

    correct answer? What information can be obtained from the Figure below? 14 12 10 pH 8 6 4 20 volume (mL) O The equivalence point occurs at pOH = 10 and the pKb = 6.0 O Both the pOH and the pKb cannot be calculated from the graph. The equivalence point occurs at pH = 8.0 and the pka = 4.0 O The equivalence point occurs at pH = 7.0 but the pka is not known from the graph.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT