Yes. The solution is correct. The calculations are as follows.
Week | 1 | 2 | 3 | 4 | Total | |
Forecast | 50 | 50 | 50 | 50 | 200 | |
Customer Orders | 60 | 30 | 65 | 25 | 180 | |
Projected Available Balance | 60 | 0 | 70 | 5 | 55 | 130 |
MPS | 100 | 100 | 200 |
The formulas used and steps for the calculations are as follows:
PAB = Prior period PAB or on-hand balance + MPS – Customer Orders
This PAB is before the demand time fence of 2 weeks. After 2 weeks, the PAB will be calculated using the following formula.
PAB for next periods = Prior PAB + MPS – customer orders or forecast whichever is greater
All calculations:
PAB for period 1: On-hand balance (inventory) is 60 units, and after satisfying the customer orders, the PAB is zero. To satisfy the demand for future products, the MPS is scheduled for lot size 100.
PAB for period 2 = 0 + 100 – 30 = 70
PAB for period 3 = 70 + 0 – 65 = 5
PAB for Period 4 = 5 + 100 – 50 = 55
is my solution correct? 3.15. Given the following data, calculate the projected available balance and the...
3.15. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The demand time fence is 2 weeks. Week Forecast 50 50 Customer Orders 1 60 30 Projected Available Balance MPS
Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Complete the following MPS time-phased record. Smell Fresh On Hand Week 1 2 3 4 5 6 7 8 Forecast 20 20 20 30 30 30 30 30 Orders 5 3 2 Projected available balance 20 50 30 10 30 50 20 40 10 Available to promise MPS 50 50 50 50 MPS Lot Size = 50 The following events...
needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...
1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...
Given the following information, the Available to Promise will show ________. Week 1 2 3 4 Forecast Demand 120 120 120 120 Actual Customer Orders 85 100 35 20 Available to Promise MPS 250 250 a. 130, 130, 130, 130 b. 165, 65, 30, 230 c. 130, 10, -110, 130 d. 30, 0, 0, 230
complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs. Problem 1: MPS and ATP A partial table for end item B is provided below. Compute the MPS for item B and then the ATP values. Complete the table and then answer the multiple-choice questions: you need to complete the table to receive full credit (even if the answers to multiple-choice questions are correct). Item B Lead Time: 1 weeks Lot Size: 80 units...