Question

3.15. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

PAB = Prior period PAB or on-hand balance + MPS – Customer Orders

PAB for period one is the on-hand balance (inventory) is 60 units, and after satisfying the customer orders, the PAB is zero. To satisfy the demand for future products, the MPS is scheduled for lot size 100.

PAB for period 2 = 0 + 100 – 30 = 70

After the demand time fence, the forecast influence the PAB, so the greater value from customer orders and forecast is considered while calculating PAB.

PAB for next periods = Prior PAB + MPS – customer orders or forecast whichever is greater

PAB for period 3 = 70 + 0 – 65 = 5

PAB for Period 4 = 5 + 100 – 50 = 55

Week

1

2

3

4

Total

Forecast

50

50

50

50

200

Customer Orders

60

30

65

25

180

Projected Available Balance

60

0

70

5

55

130

MPS

100

100

200

Add a comment
Know the answer?
Add Answer to:
3.15. Given the following data, calculate the projected available balance and the planned MPS receipts. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • is my solution correct? 3.15. Given the following data, calculate the projected available balance and the...

    is my solution correct? 3.15. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The demand time fence is 2 weeks. 4 2 3 Week 50 50 50 50 Forecast 25 30 65 60 Customer Orders 60 Projected Available Balance MPS 312 3. 15 demand time fence 2 wks lot siza = loo Week Fore cast Customer orders t0 30 Projactd Avaiabe Balano Cbo) 70 (00 LoD

  • Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products,...

    Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Complete the following MPS time-phased record. Smell Fresh On Hand Week 1 2 3 4 5 6 7 8 Forecast 20 20 20 30 30 30 30 30 Orders 5 3 2 Projected available balance 20 50 30 10 30 50 20 40 10 Available to promise MPS 50 50 50 50 MPS Lot Size = 50 The following events...

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to-...

    1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...

  • Using the following MPS record, what is the MPS start for week 7? MPS Lot Size...

    Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30

  • Given the data provided for product structure, component AC101, and the planned orders of parent AB...

    Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...

  • Product structure: Data: M(5) On Hand MPS Schedukid Receipts 150, week 3 Lot Size/ Order Policy...

    Product structure: Data: M(5) On Hand MPS Schedukid Receipts 150, week 3 Lot Size/ Order Policy FOO 800 90 | 1 740. week 5: FOQ - Fixed order quantity. "C" signifies usage. Using the data given, answ parts A and B. START by COPYING the rest of the QUESTION (from "A" to "Zzz. into the answer space. A. For Item L. fill out gross requirements, schedule receipts, projected on hand, net requirements and planned orders. Items left blank are assumed...

  • Using the following table and applying the L4L lot sizing rule, what is the projected planned...

    Using the following table and applying the L4L lot sizing rule, what is the projected planned receipts for week 3? L4L Lead Time: 1 1 2 3 4 5 6 7 8 Gross Requirements 90 20 40 60 60 Scheduled Receipts 40 Projected On-Hand Inventory 50 Planned Receipts Planned Order Releases

  • Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and...

    Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and Material Requirements Planning (MRP) Tables Bill of Material (QPA) A =Finished Good LT=1 B (1 LT-3 C(2) LT=2 D(1) LT 2 LT-2 F (2) LT-2 G (1) LT=1 Answer the following questions: 1). Fill in MPS/MRP tables provided 2). For Part Number B: What is the first period in which there is a net requirement ?:_AND, What is the net requirement Quantity (in the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT