Answer:
Please refer the formulas for filling the tables
t = current week
t-1 = previous week
scheduled receipt = SR (if given)
On-hand inventory / projected ending inventory (t) = on-hand inventory (t-1) - gross requirement (t)
(if on-hand inventory (t-1) > gross requirement (t))
On-hand inventory / projected ending inventory (t) = 0 (if on-hand inventory (t-1) <= gross requirement (t))
Net requirement (t) = 0 (if, on-hand inventory (t-1) >= gross requirement (t))
Net requirement (t) = Gross requirement (t) – [on-hand inventory (t-1) + scheduled receipt] (if, on-hand inventory (t-1) + SR(t) < gross requirement (t))
Planned receipt (t) = Net requirement (t)
Planned order release = Planned receipt (t), but offsetted ahead by lead time (i.e. if Lead time 2, planned order release will be offsetted by 2 weeks)
1) Tables for B and C are given in answers 2) and 4).
MRP Table A
Gross requirements given and for the 1st two periods, taken the greater of customer order or forecast.
Projected on hand, for period 1 = 700 - 25 (SS) = 675
2)
MRP Table B
Since planned order release of A is on week 7 and week 10.
Hence, Gross requirement for B is also on week 7 and 10. And for 1 A, 1 B is needed. Hence, quantitiy is same.
The first period in which there is net requirement? Period 7 (green cell)
What is the net requirement quantity? 210 (green cell) (Use net requirement formula given above) i.e.
300 - 90 =210
3) MRP Table F
Yes, the scheduled receipt in period 6 needs to be rescheduled.
In period 4, the scheduled receipt must be rescheduled. (see the Red arrow)
4)
MRP TABLE F
What is the first period in which there is net requirement? Period 4 (green cell)
Net requirement quantity = 1625 (2000 - 375) [refer formulas]
Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and...
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...
Given the following product tree, complete the MRP records for parts X, Y, and Z. Note that parts X and Y have specified order quantities. FILL IN THE BLANKS Note: *Gross Requirements & Net Requirements are shown as negative because demand represents withdrawals from inventory Scheduled Receipts & Planned Order Receipts are shown as positive because production represents additions to inventory 1 | 2 | 3 | 4 | 5 -15 -10 -15 -10 -15 20 71 Part X LT:...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...
12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 Item X L4L On Hand 80 Lead Time 4 70 120 85 50 70 100 Gross Requirements Scheduled Receipts On Hand Net Requirements) Planned Order Receipt Planned Order Release Styles Paragraph tem A 150 FOQ+ 30 On Hand Lead Time 8 5 2 Gross...
Please provide equation for each box 4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 Asto be available in week 5. There are 20 Bs available. All other on-hand balances =0. B(2) B (1) D(1) (1) D(2) RI) Part Number Week 3 1 2 4 5 100 Part Number Quantity B 2 D...
Download HW 15 (Excel download) and perform the necessary MRP calculations. Then enter selected values below. What is the Parent's Net Requirements for Period 5? What is the Parent's Net Requirements for Period 8? What is the Parent's Planned Order Receipts for Period 6? What is Part 1's Net Requirements for Period 8? What is the Part 1's Net Requirements for Period 5? What is the Part 1's Planned Order Release for Period 5? What is Part 2's Gross Requirements...
Case #2 MGT2315 There are two (2) Parts to this case. The First part (Part 1) requires you to use the information to:1. Build a Bill of Material (BOM) form the given information2. Determine the Master Production Schedule (MPS) and3. Complete the MRP for all parts including the product. The Second Part (Part 2) will require you to use an indexed BOM to 1. Create the correct MPS from the provided information2. create the MRP for the unit and all of...