Question

12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usag
Styles Paragraph tem A 150 FOQ+ 30 On Hand Lead Time 8 5 2 Gross Requirements Scheduled Receipts200 On Hand Net Requirements
tem B FPO 2 On Hand 320 Lead Time 6 Gross Requirements Scheduled Receipts On Hand Net Requirements Planned Order Receipt Plan
12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 Item X L4L On Hand 80 Lead Time 4 70 120 85 50 70 100 Gross Requirements Scheduled Receipts On Hand Net Requirements) Planned Order Receipt Planned Order Release
Styles Paragraph tem A 150 FOQ+ 30 On Hand Lead Time 8 5 2 Gross Requirements Scheduled Receipts200 On Hand Net Requirements Planned Order Receipt Planned Order Release
tem B FPO 2 On Hand 320 Lead Time 6 Gross Requirements Scheduled Receipts On Hand Net Requirements Planned Order Receipt Planned Order Release FOQX On Hand 250 tem C Lead Time 2 4 Gross Requirements Scheduled Receipts 650 660 On Hand Net Requirements Planned Order Receipt Planned Order Release
0 0
Add a comment Improve this question Transcribed image text
Answer #1
L4L Item X
On Hand 80
Lead Time 1
1 2 3 4 5 6 7 8
Gross Requirements 70 100 120 50 85 100 110 70
Scheduled Receipts 0 0 0 0 0 0 0 0
On Hand 10 0 0 0 0 0 0 0
Net Requirements 0 90 120 50 85 100 110 70
Planned Order Receipts 0 90 120 50 85 100 110 70
Planned Order Releases 90 120 50 85 100 110 70 0
FOQ+ 150 Item A
On Hand 30
Lead Time 1
1 2 3 4 5 6 7 8
Gross Requirements 180 240 100 170 200 220 140 0
Scheduled Receipts 200 0 0 0 0 0 0 0
On Hand 50 0 50 30 0 0 10 10
Net Requirements 0 190 100 120 170 220 140 0
Planned Order Receipts 0 190 150 150 170 220 150 0
Planned Order Releases 190 150 150 170 220 150 0 0
FPO 2 Item B
On Hand 320
Lead Time 1
1 2 3 4 5 6 7 8
Gross Requirements 190 150 150 170 220 150 0 0
Scheduled Receipts 0 0 0 0 0 0 0 0
On Hand 130 150 0 220 0 0 0 0
Net Requirements 0 20 0 170 0 150 0 0
Planned Order Receipts 0 170 0 390 0 150 0 0
Planned Order Releases 170 0 390 0 150 0 0 0
FOQx 250 Item C
On Hand 0
Lead Time 2
1 2 3 4 5 6 7 8
Gross Requirements 650 660 450 595 740 630 210 0
Scheduled Receipts 650 660 0 0 0 0 0 0
On Hand 0 0 50 205 215 85 125 125
Net Requirements 0 0 450 545 535 415 125 0
Planned Order Receipts 0 0 500 750 750 500 250 0
Planned Order Releases 500 750 750 500 250 0 0 0
Add a comment
Know the answer?
Add Answer to:
12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 It...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct...

    Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • Given the data provided for product structure, component AC101, and the planned orders of parent AB...

    Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...

  • Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using...

    Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using a L4L lot-sizing strategy. Repeat using a fixed order quantity of 106 frames. Compare and contrast the results. What are the benefits and drawbacks to each approach? (Leave no cells blank - be certain to enter "O" wherever required.) picture Click here for the Excel Data File Part Name: Bicycle frame Week 6 Week 5 Week 7 Week 8 Week 1 Week 3 Week...

  • Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time =...

    Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On-hand = 40 Safety stock = 20 Order quantity: FOQ = 100 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 70 50 80 80 70 60 80 80 Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releases

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty seven units of Product Z are required in Period 10. (Assume that...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT