Question

Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the required MRP schedule -

AB500
LT 2
Q = L4L
On Hand 1 2 3 4 5 6 7 8 9 10
Gross Requirement 0 0 210 250 150 250 150 250 150 250
Scheduled Receipts 0 0 0 0 0 0 0 0 0 0
Projected on Hand 60 60 60 0 0 0 0 0 0 0 0
Net Requirements 0 0 150 250 150 250 150 250 150 250
Planned Order Receipts 0 0 150 250 150 250 150 250 150 250
Planned Order Releases 150 250 150 250 150 250 150 250 0 0
AC101
LT 3
Q = 600
Gross Requirement 300 500 300 500 300 500 300 500 0 0
Scheduled Receipts 0 0 0 0 0 600 0 0 0 0
Projected on Hand 1300 1000 500 200 500 200 300 0 100 100 100
Net Requirements 0 0 0 300 0 0 0 500 0 0
Planned Order Receipts 0 0 0 800 0 0 0 600 0 0
Planned Order Releases 600 0 0 0 600 0 0 0 0 0

Below is the screenshot of the MRP schedule -

mos - Excel BS File Home Insert Page Layout Formulas Data Review View Help Tell me what you want to do General Cut EL Copy Fo

Add a comment
Know the answer?
Add Answer to:
Given the data provided for product structure, component AC101, and the planned orders of parent AB...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • Product structure: Data: M(5) On Hand MPS Schedukid Receipts 150, week 3 Lot Size/ Order Policy...

    Product structure: Data: M(5) On Hand MPS Schedukid Receipts 150, week 3 Lot Size/ Order Policy FOO 800 90 | 1 740. week 5: FOQ - Fixed order quantity. "C" signifies usage. Using the data given, answ parts A and B. START by COPYING the rest of the QUESTION (from "A" to "Zzz. into the answer space. A. For Item L. fill out gross requirements, schedule receipts, projected on hand, net requirements and planned orders. Items left blank are assumed...

  • Problem 14-5 To simplify data handling to include the receipt of orders that have actually been...

    Problem 14-5 To simplify data handling to include the receipt of orders that have actually been placed in previous periods, the following six-level scheme can be used. (A number of different techniques are used in practice, but the important issue is to keep track of what is on hand, what is expected to arrive, what is needed, and what size orders should be placed.)      One unit of A is made of three units of B, one unit of C, and...

  • One unit of A is made of three units of B, one unit of C, and...

    One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty seven units of Product Z are required in Period 10. (Assume that...

  • Assume that Product Z is made of two units of A and three units of B. A is made of four units of ...

    Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty one units of Product Z are required in Period 10. (Assume that...

  • One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of tw...

    One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...

  • One unit of A is made of two units of B and one unit of C....

    One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT