Question

One unit of A is made of three units of B, one unit of C, and...

One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F.

Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks.

Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 50, 50, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 150, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 2, 50 units of E in Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If 30 units of A are required in Week 8, use the low-level-coded bill-of-materials to find the necessary planned order releases for all components.


Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.)

Period 1 2 3 4 5 6 7 8
Item A
OH = 0
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item C
OH = 10
LT = 1
SS = 0
Q = 50
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item B
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item D
OH = 0
LT = 2
SS = 0
Q = 50
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item E
OH = 50
LT = 1
SS = 0
Q = 200
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item F
OH = 150
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the screenshot of the MRP schedule -

XI 5 = mos - Excel Dynamics AX FILE HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Calibri T 11 AA Wrap Text General * Cutx5 – mos - Excel Dynamics AX FILE HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Calibri T 11 A A Wrap Text General A * Cu

Below is the screenshot of the formula applied -

XJ 5 mos - Excel ? FILE Abhishek Rai fx Calculate Now HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Dynamics AX Σ ? A e DXUS ? mos - Excel Dynamics AX FILE HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Abhishek Rai fx Σ Calculate Now Insert F

Add a comment
Know the answer?
Add Answer to:
One unit of A is made of three units of B, one unit of C, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT