Question

Assume that Product Z is made of two units of A and three units of B. A is made of four units of ...

Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E

     Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

     Fifty one units of Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)


b. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.)


Period 1 2 3 4 5 6 7 8 9 10
Item Z
OH = 0
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item A
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item B
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item C
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item D
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item E
OH = 0
LT = 3
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Steps to create the MRP 1) Enter the gross requirement as per Master Planning Schedule (MPS). Gross requirement of components

MRP 10 4 Item 51 Gross Requirement Scheduled Receipt Proiected on Hand Net Requirement 2 Planned Order Receipt SOR = 51 ss =

Item 10 Gross Requirement Scheduled Receipt Proiected on Hand Net Requirement 1 Planned Order Receipt Planned Order Release 4

Add a comment
Know the answer?
Add Answer to:
Assume that Product Z is made of two units of A and three units of B. A is made of four units of ...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT