Question

One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item...

One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of three weeks. Lot-for-lot lot sizing is used for Items A, D, and E; lots of size 50, 100, and 48 are used for Items B, C, and F, respectively. Items A, C, D, and E have on-hand (beginning) inventories of 20, 50, 100, and 20, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 1, 100 units of C in Week 1, and 100 units of D in Week 3; there are no other scheduled receipts.


If 40 units of A are required in Week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned order releases for all components. (Leave no cells blank - be certain to enter "0" wherever required.)

  

Period 1 2 3 4 5 6 7 8 9 10
Item A
OH = 20
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item B
OH = 0
LT = 2
SS = 0
Q = 50
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item C
OH = 50
LT = 1
SS = 0
Q = 100
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item D
OH = 100
LT = 3
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item E
OH = 20
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item F
OH = 0
LT = 2
SS = 0
Q = 48
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the required MRP schedule -

A
LT 2
Q = L4L
On Hand 1 2 3 4 5 6 7 8 9 10
Gross Requirement 0 0 0 0 0 0 0 0 0 40
Scheduled Receipts 10 0 0 0 0 0 0 0 0 0
Projected on Hand 20 30 30 30 30 30 30 30 30 30 0
Net Requirements 0 0 0 0 0 0 0 0 0 10
Planned Order Receipts 0 0 0 0 0 0 0 0 0 10
Planned Order Releases 0 0 0 0 0 0 0 10 0 0
B
LT 2
Q = 50
Gross Requirement 0 0 0 0 0 0 0 10 0 0
Scheduled Receipts 0 0 0 0 0 0 0 0 0 0
Projected on Hand 0 0 0 0 0 0 0 0 40 40 40
Net Requirements 0 0 0 0 0 0 0 10 0 0
Planned Order Receipts 0 0 0 0 0 0 0 50 0 0
Planned Order Releases 0 0 0 0 0 50 0 0 0 0
C
LT 1
Q = 100
Gross Requirement 0 0 0 0 0 200 0 10 0 0
Scheduled Receipts 100 0 0 0 0 0 0 0 0 0
Projected on Hand 50 150 150 150 150 150 50 50 40 40 40
Net Requirements 0 0 0 0 0 50 0 0 0 0
Planned Order Receipts 0 0 0 0 0 100 0 0 0 0
Planned Order Releases 0 0 0 0 100 0 0 0 0 0
D
LT 3
Q = L4L
Gross Requirement 0 0 0 0 200 0 0 0 0 0
Scheduled Receipts 0 0 100 0 0 0 0 0 0 0
Projected on Hand 100 100 100 200 200 0 0 0 0 0 0
Net Requirements 0 0 0 0 0 0 0 0 0 0
Planned Order Receipts 0 0 0 0 0 0 0 0 0 0
Planned Order Releases 0 0 0 0 0 0 0 0 0 0
E
LT 2
Q = L4L
Gross Requirement 0 0 0 0 100 50 0 0 0 0
Scheduled Receipts 0 0 0 0 0 0 0 0 0 0
Projected on Hand 20 20 20 20 20 0 0 0 0 0 0
Net Requirements 0 0 0 0 80 50 0 0 0 0
Planned Order Receipts 0 0 0 0 80 50 0 0 0 0
Planned Order Releases 0 0 80 50 0 0 0 0 0 0
F
LT 2
Q = 48
Gross Requirement 0 0 240 150 0 50 0 0 0 0
Scheduled Receipts 0 0 0 0 0 0 0 0 0 0
Projected on Hand 0 0 0 0 42 42 40 40 40 40 40
Net Requirements 0 0 240 150 0 8 0 0 0 0
Planned Order Receipts 0 0 240 192 0 48 0 0 0 0
Planned Order Releases 240 192 0 48 0 0 0 0 0 0
Add a comment
Know the answer?
Add Answer to:
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT