Question

One unit of A is made of two units of B and one unit of C....

One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for Items C, E, and F; lots of size 20, 40, and 160 are used for Items A, B, and D, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 5, 10, 100, and 100, respectively; all other items have zero beginning inventories. We are scheduled to receive 10 units of A in Week 3, 20 units of B in Week 7, 40 units of F in Week 5, and 60 units of E in Week 2; there are no other scheduled receipts.


If 20 units of A are required in Week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned order releases for all components. (Leave no cells blank - be certain to enter "0" wherever required.)

Period 1 2 3 4 5 6 7 8 9 10
Item A
OH = 5
LT = 2
SS = 0
Q = 20
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item C
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item B
OH = 10
LT = 2
SS = 0
Q = 40
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item D
OH = 100
LT = 3
SS = 0
Q = 160
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item F
OH = 0
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item E
OH = 100
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
0 1
Add a comment Improve this question Transcribed image text
Answer #1

The product structre is as under:

А B(2) C(1) D(3) F(1) B(3) D(1) E(4) E(1)

Item

Lead time (weeks)

Lot size

On hand (beginning)

Scheduled receipts

A

2

20

5

10 units week 3

B

2

40

10

20 units week 7

C

1

L4L

0

0

D

3

160

100

0

E

2

L4L

100

60 units week 2

F

2

L4L

0

40 units week 5

MRP planning schedule:

Period 1 2 3 4 5 6 7 8 9 10 Item A OH = 5 LT = 2 SS = 0 Q = 20 Gross requirements Scheduled receipts Projected available bala

Period 1 2 3 4 5 6 7 8 9 10 Item B OH = 10 LT = 2 SS = 0 Q = 40 Gross requirements Scheduled receipts Projected available bal

Period 1 2 3 4 5 6 7 8 9 10 Item F OH = 0 LT = 2 0 0 0 0 40 40 0 0 0 0 0 0 0 0 0 0 0 0 0 SS=0 Q = L4L Gross requirements Sche

Projected available balance = Previous period closing stock + Scheduled receipts + Planned order receipts – Gross requirements

Planned receipts are the quantity to be delivered when the Project on hand inventory quantity is negative (so that it becomes equal to or more than zero and is based on lot size). Freshly planned.

Planned order release is the order issued based on the lot size and lead time.

Net requirement is the quantity actually short (if any).

------------------------------------------------------------------------

Note: If you liked the answer please give an Up-vote, this will be quite encouraging for me, thank you!

Add a comment
Know the answer?
Add Answer to:
One unit of A is made of two units of B and one unit of C....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT