Question

One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit ofItem E OH 80 LT-1 SS = 0 Q-180Planned order receipts Gross requirements Scheduled receipts Projected available balance Net re

One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 65, 65, and 180 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 12, 80, and 150, respectively; all other items have zero beginning inventory. We are scheduled to receive 9 units of A in Week 2, 50 units of E in Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If 35 units of A are required in Week 8, use the low-level-coded bill of materials to find the necessary planned order releases for all components Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank- be certain to enter "O" wherever required.) Period Gross requirements Scheduled receipts Projected available balance Item A OH 0 LT-2 SS 0Net requirements Q-L4LPlanned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item C он 12 し7-1 Item B LT=1 Q=L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item D LT 2 Q-65 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases
Item E OH 80 LT-1 SS = 0 Q-180Planned order receipts Gross requirements Scheduled receipts Projected available balance Net requirements Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item F OH-150 LT=1 8 Q.L4L
0 0
Add a comment Improve this question Transcribed image text
Answer #1

We will assume that projected available balance means that the beginning inventory at that period. Since no specific instruction is given, projected available balance is sometimes taken at the end of the period or before the period. At this point, we will assume it is at the beginning of the period.

Based on this, the MRP is shown below

Period 1 2 3 4 5 6 7 8
Gross requirement 0 0 0 0 0 0 0 35
Item A Scheduled receipts 0 9 0 0 0 0 0 0
OH = 0 Projected available balance 0 9 9 9 9 9 9 9
LT = 2 Net requirements 0 0 0 0 0 0 0 26
SS = 0 Planned order receipts 0 0 0 0 0 0 0 26
Q = L4L Planned order release 0 0 0 0 0 26 0 0
Gross requirement 0 0 0 0 0 26 0 0
Item C Scheduled receipts 0 0 0 0 0 0 0 0
OH = 12 Projected available balance 12 12 12 12 12 12 51 51
LT = 1 Net requirements 0 0 0 0 0 14 0 0
SS = 0 Planned order receipts 0 0 0 0 0 65 0 0
Q = 65 Planned order release 0 0 0 0 65 0 0 0
Gross requirement 0 0 0 0 65 78 0 0
Item B Scheduled receipts 0 0 0 0 0 0 0 0
OH = 0 Projected available balance 0 0 0 0 0 0 0 0
LT = 1 Net requirements 0 0 0 0 65 78 0 0
SS = 0 Planned order receipts 0 0 0 0 65 78 0 0
Q = L4L Planned order release 0 0 0 65 78 0 0 0
Gross requirement 0 0 0 65 78 52 0 0
Item D Scheduled receipts 0 0 0 0 0 0 0 0
OH = 0 Projected available balance 0 0 0 0 0 0 0 0
LT = 2 Net requirements 0 0 0 65 78 52 0 0
SS = 0 Planned order receipts 0 0 0 65 78 52 0 0
Q = 65 Planned order release 0 65 78 52 0 0 0 0
Gross requirement 0 0 0 130 156 52 0 0
Item E Scheduled receipts 50 0 0 0 0 0 0 0
OH = 80 Projected available balance 80 130 130 130 0 24 152 152
LT = 1 Net requirements 0 0 0 0 156 28 0 0
SS = 0 Planned order receipts 0 0 0 0 180 180 0 0
Q = 180 Planned order release 0 0 0 180 180 0 0 0
Gross requirement 0 0 0 180 180 0 0 0
Item F Scheduled receipts 50 0 0 0 0 0 0 0
OH = 150 Projected available balance 0 50 50 50 0 0 0 0
LT = 1 Net requirements 0 0 0 130 180 0 0 0
SS = 0 Planned order receipts 0 0 0 130 180 0 0 0
Q = L4L Planned order release 0 0 130 180 0 0 0 0
Add a comment
Know the answer?
Add Answer to:
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of tw...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT