Question

provide step by step explanation of calculation. thanks

Case #2 MGT2315

 

There are two (2) Parts to this case.

 

The First part (Part 1) requires you to use the information to:

1.    Build a Bill of Material (BOM) form the given information

2.    Determine the Master Production Schedule (MPS) and

3.    Complete the MRP for all parts including the product.

 

 

 

The Second Part (Part 2) will require you to use an indexed BOM to

1.    Create the correct MPS from the provided information

2.    create the MRP for the unit and all of its assemblies/components

 

 

The marks will be awarded as indicated below’

 

Part 1:

Item

Marks available

Marks Awarded

Part 1



Correct BOM

5


Correct MPS for Product

2


Correct Gross requirement for each   part

9


Correct Planned Order release for   each part

9


Total   Part 1

25





Part 2



Correct Gross requirement for each   part

12


Correct Planned Order release for   each part

13


Total   Part 2

25





Total for Case

50






 

Part 1: BOM and MRP (25 marks)

 

Product XYZ is described as follows: Quantity of each assembly/component is in (brackets)

 

XYZ are made up of assemblies A(3), B, & C(2)

 

Assembly A contains D(2), E(2), & F(3)

 

Assembly B contains part H(2)

 

Assembly C contains parts G(2) & E(2)

 

Inventory Lead- time and Lot Size Information:

 


XYZ

A

B

C

D

E

F

G

H

Lead Time

1

2

1

1

1

2

2

2

2

Projected On Hand

93

125

32

92

520

391

600

125

68

Lot Size

LFL

LFL

20

10

LFL

100

200

100

50

Scheduled Receipts

50

0

0

0

0

0

0

100

0

Safety Stock 



10



50


25


 

**Note** all scheduled receipts are in week 1

 

  1. Create a product structure tree (Multilevel BOM):       (5 marks)

 

Using Blank MRP sheets,

 

  1. Create a level loaded (discreet, with no remnants) plan      for XYZ’s based on a MPS of 40 per week (plan must be a minimum of 8      weeks).level 0 MPS  (2 marks)

  2. Create and complete an MRP plan for each item in the      product tree. (18 marks)

 

 


 

Part 2

Bruce’s Fans has just released an order for 500 50-cm fans due week 5 and 800 50-cm fans due week 7. Each fan consists of a housing assembly, 2 grills, a fan assembly, and an electrical unit. The breakdown of the assemblies and components is shown below. Quantities are numbers within (x). Using the information from the following table and the blank MRP sheets, construct the MRP Plan for the 50-cm Fan

Component

Lead   Time

On hand   Inventory

Lot Size

Safety   Stock

Scheduled   Receipts

50-cm Fan

1

100

LFL



       Housing

1

100

LFL



              Frame

2

0

LFL



              Supports (2)

1

50

100



              Handle

1

400

500



       Grills (2)

2

200

500



       Fan Assembly

3

150

LFL



              Hub

1

300

LFL



              Blades (5)

2

1400

100



       Electrical Unit

1

0

LFL



              Motor

1

0

LFL



              Switch

1

20

12



              Knob

1

0

15


200 Week   2

 

for MRP: excel sheet

 
Q=
LS=
SS=
LT=1


XYZ
WK1WK2WK3WK4WK5WK6WK7WK8WK9WK10WK11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



A
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



B
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



C
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



D
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



E
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

















































F
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

















































G
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases










for BOM: 

 
Q=1LS=
SS=
LT=1


A
WK1WK2WK3WK4WK5WK6WK7WK8WK9WK10WK11
Gross Requirements










Scheduled Receipts










Projected On   Hand











Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



B
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand10










Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



C
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand40










Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



D
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand180










Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



E
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand400










Net Requirements










Planned Order   Receipts










Planned Order   Releases

























Q=
LS=
SS=
LT=



F
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11
Gross Requirements










Scheduled Receipts










Projected On   Hand50










Net Requirements










Planned Order   Receipts










Planned Order   Releases











0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

11 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
provide step by step explanation of calculation. thanks
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • PLEASE PROVIDE STEP BY STEP CALCULATION PERFORMED IN EXCEL.

    Product XYZ is described as follows: Quantity of each assembly/component is in (brackets) XYZ are made up of assemblies A(3), B, & C(2) Assembly A contains D(2), E(2), & F(3) Assembly B contains part H(2) Assembly C contains parts G(2) & E(2) Inventory Lead- time and Lot Size Information: XYZABCDEFGHLead Time121112222Projected On Hand93125329252039160012568Lot SizeLFLLFL2010LFL10020010050Scheduled Receipts500000001000Safety Stock 105025 **Note** all scheduled receipts are in week 1 Create a product structure tree (Multilevel BOM):       (5 marks) Using Blank MRP sheets, Create a level loaded (discreet, with no remnants) plan    ...

  • supply chain question, please solve it anyone.

    There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of its assemblies/components Part 1:...

  • Assume that Product Z is made of two units of A and three units of B. A is made of four units of ...

    Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty one units of Product Z are required in Period 10. (Assume that...

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty seven units of Product Z are required in Period 10. (Assume that...

  • One unit of A is made of three units of B, one unit of C, and...

    One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...

  • One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of tw...

    One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • One unit of A is made of two units of B and one unit of C....

    One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...

  • One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item...

    One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT