Using the following table and applying the L4L lot sizing rule, what is the projected planned receipts for week 3? L4L Lead Time: 1 1 2 3 4 5 6 7 8 Gross Requirements 90 20 40 60 60 Scheduled Receipts 40 Projected On-Hand Inventory 50 Planned Receipts Planned Order Releases
Below is required MRP schedule -
LT = 1 Q = L4L |
On Hand | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Gross Requirement | 90 | 0 | 20 | 40 | 0 | 60 | 0 | 60 | ||
Scheduled Receipts | 40 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
Projected on Hand | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Net Requirements | 0 | 0 | 20 | 40 | 0 | 60 | 0 | 60 | ||
Planned Order Receipts | 0 | 0 | 20 | 40 | 0 | 60 | 0 | 60 | ||
Planned Order Releases | 0 | 20 | 40 | 0 | 60 | 0 | 60 | 0 |
Planned receipts for week 3 = 20 units
Using the following table and applying the L4L lot sizing rule, what is the projected planned...
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19? For the Office Table above, what are the Planned Order Receipts in the week of 8/8? For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19? For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5? We were unable to transcribe this imageMS.53 An office...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
i Data Table Table 2. INVENTORY RECORD DATA F G C Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts Beginning inventory L4L 3 weeks 0 150 (week 2) 125 D FOQ = 800 3 weeks 0 300 (week 2) 0 Item E FOQ = 600 4 weeks 0 600 (week 1) 255 L4L 2 weeks 70 None 670 L4L 1 week 0 1,200 (week 1) 0 Print Done Done nd then click Check Answer. Clear All The BOM...