Question

Using the following table and applying the L4L lot sizing rule, what is the projected planned...

Using the following table and applying the L4L lot sizing rule, what is the projected planned receipts for week 3? L4L Lead Time: 1 1 2 3 4 5 6 7 8 Gross Requirements 90 20 40 60 60 Scheduled Receipts 40 Projected On-Hand Inventory 50 Planned Receipts Planned Order Releases

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is required MRP schedule -

LT = 1
Q = L4L
On Hand 1 2 3 4 5 6 7 8
Gross Requirement 90 0 20 40 0 60 0 60
Scheduled Receipts 40 0 0 0 0 0 0 0
Projected on Hand 50 0 0 0 0 0 0 0 0
Net Requirements 0 0 20 40 0 60 0 60
Planned Order Receipts 0 0 20 40 0 60 0 60
Planned Order Releases 0 20 40 0 60 0 60 0

Planned receipts for week 3 = 20 units

Add a comment
Know the answer?
Add Answer to:
Using the following table and applying the L4L lot sizing rule, what is the projected planned...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT