Question #3
Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter.
Smell Fresh |
On Hand |
Week |
|||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
||
Forecast |
20 |
20 |
20 |
30 |
30 |
30 |
30 |
30 |
|
Orders |
5 |
3 |
2 |
||||||
Projected available balance |
20 |
50 |
30 |
10 |
30 |
50 |
20 |
40 |
10 |
Available to promise |
|||||||||
MPS |
50 |
50 |
50 |
50 |
MPS Lot Size = 50
Update the record below after rolling through time.
Smell Fresh |
On Hand |
Week |
|||||||
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
||
Forecast |
|||||||||
Orders |
|||||||||
Projected available balance |
60 (Hint) |
||||||||
Available to promise |
|||||||||
MPS |
MPS Lot Size = 50
(a)
Smell Fresh | On Hand | Week | |||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
Forecast | 20 | 20 | 20 | 30 | 30 | 30 | 30 | 30 | |
Orders | 5 | 3 | 2 | 0 | 0 | 0 | 0 | 0 | |
Projected Avl Bal. | 20 | 50 | 30 | 10 | 30 | 50 | 20 | 40 | 10 |
Available to promise | 60 | 50 | 50 | 50 | |||||
MPS | 50 | 50 | 50 | 50 |
Note:
ATP for the first period = Beginning Inventory + MPS of the first period - Sum of orders up to the next MPS.
ATP for other periods = MPS of that period - Sum of orders up to the next MPS.
(b)
Smell Fresh | On Hand | |||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
Forecast | 20 | 20 | 30 | 30 | 30 | 30 | 30 | |
Orders | 15 | 10 | 25 | 0 | 0 | 0 | 0 | |
Projected Avl Bal. | 60 | 40 | 20 | 40 | 60 | 30 | 50 | 20 |
Available to promise | 35 | 25 | 50 | 50 | ||||
MPS | 50 | 50 | 50 |
Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products,...
Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30
Assignment 8 is due on Sunday 8/2 at 11:00 AM Complete the following MPS record and find out what is the available-to-promise. There are 20 units in beginning inventory and the lot size is 50. Answer in Excel and submit your answer in the drop box. Period 1 2 3 4 5 6 Forecast 20 22 23 20 25 20 Customers order (committed) 21 20 21 23 208 POH (Projected on hand) MPS (Master production schedule) ATP (Available-to-promise)
1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...
needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...
Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...
3.15. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The demand time fence is 2 weeks. Week Forecast 50 50 Customer Orders 1 60 30 Projected Available Balance MPS
I need the Mps quantity and MPS start % Problem 1 Questi Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: week Quantity Week on Hand: 30 1 2 4 6 7 8 3 28 5 23 22 18 31 27 31 32 13 17 7 17 11 0 9 0 Forecast Customer orders (booked) Projected on-hand...
Show work Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots of 100. Show all your calculations on the paper to receive full or partial credits. Week Quantity on hand: 40 1 Forecast 40|40|40|40|50 50 | 50 | 50 Customer orders (booked)20 95 40 45 15 75 20 10 Projected on-hand Inventory MPS...
Problem 1 Week 1 2 3 4 5 6 7 8 9 10 Forecast 65 70 60 65 70 65 65 60 55 40 Customer Orders 20 25 10 40 10 30 5 10 0 5 Available 100 Average PAB (w/out starting) ATP Total ATP MPS Total MPS On hand = 100 Lot size = 100 multiples Safety Stock = 25 1. Complete the MPS time-phased record above with the information as given
Question 1 (2-Part) a) Complete the MPS record below for a single item. (Enter your responses as integers. A response of 0is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: 1 week on Hand: 35 20 28 28 30 35 18 Customer orders 17 17 MPS quantity MPS start b) Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response...