Question

Problem 1 Week 1 2 3 4 5 6 7 8 9 10 Forecast 65 70...

Problem 1

Week

1

2

3

4

5

6

7

8

9

10

Forecast

65

70

60

65

70

65

65

60

55

40

Customer Orders

20

25

10

40

10

30

5

10

0

5

Available

100

Average PAB (w/out starting)

ATP

Total ATP

MPS

Total MPS

On hand = 100

Lot size = 100 multiples

Safety Stock = 25

1. Complete the MPS time-phased record above with the information as given

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Week Forecast Customer Orders Available ATP MPS On hand100 12345678910 65 70065 70 65 6055 40 20 25 04010 30 51005 100 35 610

Steps

1. Compute the Available balance row first using the formula

Available balance = Available balance of previous period + MPS - Max.(Forecast, Orders)

2. Insert MPS = 100 or multiples wherever available balance is less than the safety stock.

3. Compute the ATP of the first period as ATP1 = On-hand + MPS1 - Order up to the next MPS = 100 + 0 - 20 = 80

4. Compute the ATP of the other periods as ATPt = MPSt - Order up to the next MPS

Add a comment
Know the answer?
Add Answer to:
Problem 1 Week 1 2 3 4 5 6 7 8 9 10 Forecast 65 70...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information...

    Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information in the following table, prepare a prospective MPS and calculate the available-to-promise quantities. The order policy is to produce in lots of 300. 1 100 40 2 100 190 3 100 220 Week 4 5 100 120 70 60 6 120 110 7 120 40 8 120 Quantity on hand: 100 Forecast Customer orders (CO) Projected on-hand inventory MPS quantity Available-to-promise (ATP) Assume that...

  • Using the following MPS record, what is the MPS start for week 7? MPS Lot Size...

    Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30

  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2,16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on- hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used (Leave no cells blank - be...

  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank - be...

  • Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and...

    Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products,...

    Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Complete the following MPS time-phased record. Smell Fresh On Hand Week 1 2 3 4 5 6 7 8 Forecast 20 20 20 30 30 30 30 30 Orders 5 3 2 Projected available balance 20 50 30 10 30 50 20 40 10 Available to promise MPS 50 50 50 50 MPS Lot Size = 50 The following events...

  • is my solution correct? 3.15. Given the following data, calculate the projected available balance and the...

    is my solution correct? 3.15. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The demand time fence is 2 weeks. 4 2 3 Week 50 50 50 50 Forecast 25 30 65 60 Customer Orders 60 Projected Available Balance MPS 312 3. 15 demand time fence 2 wks lot siza = loo Week Fore cast Customer orders t0 30 Projactd Avaiabe Balano Cbo) 70 (00 LoD

  • Prepare a master production schedule for industrial pumps in the manner of the following ta Use...

    Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...

  • Show work Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare...

    Show work Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots of 100. Show all your calculations on the paper to receive full or partial credits. Week Quantity on hand: 40 1 Forecast 40|40|40|40|50 50 | 50 | 50 Customer orders (booked)20 95 40 45 15 75 20 10 Projected on-hand Inventory MPS...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT