Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots of 100. Show all your calculations on the paper to receive full or partial credits. Week Quantity on hand: 40 1 Forecast 40|40|40|40|50 50 | 50 | 50 Customer orders (booked)20 95 40 45 15 75 20 10 Projected on-hand Inventory MPS quantity Available-to-promise (ATP) Based on the ATP, should a new customer order of 50 units, to be delivered in week 4, be accepted? If not, which week is the earliest that this order can be accepted? Show work
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Week 1 2 3 4 5 6 7 8
Forecast 40 40 40 40 50 50 50 50
Orders 20 95 40 45 15 75 20 10
Inv on hand 0 5 65 20 70 95 45 95
MPS Qty 0 100 100 0 100 100 0 100
ATP 0 5 15 0 85 5 0 90

In week 1 there will be no production as the requirement of 40 units will be met through invntory on hand.

In week 2, 100 units will be produced, out of which 95 will be utilised for order and 5 on hand. ATP will be 5 units, which can be provided to a customer if needed.

In week 3, again 100 units will be produced leaving 65 on hand, but available to promise will be (100- 40-45) because in addition to meeting requirements of week 3, the week 4 requirements will also be met through this production cycle only as week 4 has no production schedule.

In the same way, data for week 5, 6, 7 and 8 can also be calculated as in table above.

New customer's order of 50 units can not be fulfilled in week4, as it has no ATP. The order can only be fulfilled in week 5, where 85 units are available.

Add a comment
Know the answer?
Add Answer to:
Show work Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to-...

    1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...

  • Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information...

    Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information in the following table, prepare a prospective MPS and calculate the available-to-promise quantities. The order policy is to produce in lots of 300. 1 100 40 2 100 190 3 100 220 Week 4 5 100 120 70 60 6 120 110 7 120 40 8 120 Quantity on hand: 100 Forecast Customer orders (CO) Projected on-hand inventory MPS quantity Available-to-promise (ATP) Assume that...

  • Using the following MPS record, what is the MPS start for week 7? MPS Lot Size...

    Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products,...

    Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Complete the following MPS time-phased record. Smell Fresh On Hand Week 1 2 3 4 5 6 7 8 Forecast 20 20 20 30 30 30 30 30 Orders 5 3 2 Projected available balance 20 50 30 10 30 50 20 40 10 Available to promise MPS 50 50 50 50 MPS Lot Size = 50 The following events...

  • complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs....

    complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs. Problem 1: MPS and ATP A partial table for end item B is provided below. Compute the MPS for item B and then the ATP values. Complete the table and then answer the multiple-choice questions: you need to complete the table to receive full credit (even if the answers to multiple-choice questions are correct). Item B Lead Time: 1 weeks Lot Size: 80 units...

  • Prepare a master production schedule for industrial pumps in the manner of the following ta Use...

    Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...

  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2,16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on- hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used (Leave no cells blank - be...

  • Prepare a master production schedule for industrial pumps in the manner of the following table. U...

    Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production, Suppose that a production lot size of 70 pumps is used (Leave no cells blank- be certain to enter "O wherever required.) June 64 Forecast Customer orders (commitied) Projected on-hand inventory MPS ATP 30 30 40 40 30 20 30 10 References eBook & Resources Worksheet...

  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank - be...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT