Formula
Order 1 which is 70 quantity in week 6 can be accepted since We can fulfill that from 90 quantity of ATP generated in period 5
Order 2 which is 60 quantity in week 1 can be accepted as it can be accommodated from 60 ATP of week 1
order 3 which is 80 quantity in week 3 also can be accepted as it can be accepted by taking 170 quantity from 110 ATP quantity generated in week 2 and 10 quantity from ATP generated in week 3
Order 4 50 quantity in week 7 also can be accepted by taking
remaining 20 ATP from Week 6 and 30 quantity from week 2
So correct answer is a) all of the orders
ATP schedule changed after the orders as below
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Demand | 100 | 100 | 100 | 100 | 120 | 120 | 120 | 120 |
Customer Orders | 100 | 190 | 300 | 70 | 60 | 180 | 90 | 0 |
Requirement | 100 | 190 | 300 | 100 | 120 | 180 | 120 | 120 |
Opening Inventory | 100 | 0 | 110 | 110 | 10 | 190 | 10 | 190 |
Net Inventory before production | 0 | -190 | -190 | 10 | -110 | 10 | -110 | 70 |
Master Production Schedule | 0 | 300 | 300 | 0 | 300 | 0 | 300 | 0 |
Projected On-Hand Inventory (POHI) at the end of period | 0 | 110 | 110 | 10 | 190 | 10 | 190 | 70 |
Available To Promise | 0 | 10 | 0 | 0 | 0 | 0 | 300 |
Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information...
Show work Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots of 100. Show all your calculations on the paper to receive full or partial credits. Week Quantity on hand: 40 1 Forecast 40|40|40|40|50 50 | 50 | 50 Customer orders (booked)20 95 40 45 15 75 20 10 Projected on-hand Inventory MPS...
1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...
needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...
Problem 1 Week 1 2 3 4 5 6 7 8 9 10 Forecast 65 70 60 65 70 65 65 60 55 40 Customer Orders 20 25 10 40 10 30 5 10 0 5 Available 100 Average PAB (w/out starting) ATP Total ATP MPS Total MPS On hand = 100 Lot size = 100 multiples Safety Stock = 25 1. Complete the MPS time-phased record above with the information as given
Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...
Question 1 (2-Part) a) Complete the MPS record below for a single item. (Enter your responses as integers. A response of 0is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: 1 week on Hand: 35 20 28 28 30 35 18 Customer orders 17 17 MPS quantity MPS start b) Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response...
Given the following information, the Available to Promise will show ________. Week 1 2 3 4 Forecast Demand 120 120 120 120 Actual Customer Orders 85 100 35 20 Available to Promise MPS 250 250 a. 130, 130, 130, 130 b. 165, 65, 30, 230 c. 130, 10, -110, 130 d. 30, 0, 0, 230
Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30
I need the Mps quantity and MPS start % Problem 1 Questi Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: week Quantity Week on Hand: 30 1 2 4 6 7 8 3 28 5 23 22 18 31 27 31 32 13 17 7 17 11 0 9 0 Forecast Customer orders (booked) Projected on-hand...
Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...