Question

Question 1 (2-Part) a) Complete the MPS record below for a single item. (Enter your responses as integers. A response of 0is

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Qa.

Projected on-hand after MPS = Previous week Inventory + MPS – Week Requirements

Where, week requirement = maximum (forecast, Orders)

POH = beginning inv + MPS – maximum (Forecast, customer orders)

Before placing MPS if the POH is negative , then place order of 60 units in that week. Update the POH again after placing MPS order.

(for week 2, before MPS the POH = 17 – max(20,17) = -3, thus the MPS of Q = 60 is placed and POH is updated)

Order Policy =

60

Beginning Inventory =

35

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

Forecast

18

20

28

28

21

30

36

35

Orders

15

17

11

17

9

0

11

0

Projected On-Hand

35-max(18,15)

= 17

17+60- max(20,17)

= 57

29

1

40

10

34

59

Master Production Schedule

0

60

0

0

60

0

60

60

MPS Start

60

0

0

60

0

60

60

0

Since the Lead time is 1 week, the MPs will start 1 week prior to MPS placed.

Qb.a

Projected on-hand after MPS = Previous week Inventory + MPS – Week Requirements

Where, week requirement = maximum (forecast, Orders)

POH = beginning inv + MPS – maximum (Forecast, customer orders)

Before placing MPS if the POH is negative , then place order of 60 units in that week. Update the POH again after placing MPS order.

(for week 2, before MPS the POH = 17 – max(20,17) = -3, thus the MPS of Q = 60 is placed and POH is updated)

Available to promise (ATP)

For first week: ATP = Beg. Inv + MPS for first week - sum of orders for weeks till next MPS is scheduled

For remaining week: ATP = MPS for a week - sum of orders for weeks till next MPS is scheduled

(the week in which MPS is not scheduled, the ATP will remain same as previous weeks)

Order Policy =

500

Beginning Inventory =

400

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

Week 9

Week 10

Forecast

550

300

350

400

300

400

200

350

500

450

Orders

300

350

250

250

200

100

150

100

150

100

Projected On-Hand

400+500-Max(550,300)

= 350

0

150

250

450

50

350

0

0

50

Master Production Schedule

500

0

500

500

500

0

500

0

500

500

MPS Start

500

0

500

500

500

0

500

0

500

Available-to-Promise

400+500

-(300+350)

= 250

500-(250)

= 250

250

200

250

350

400

Qb.b

Order

Quantity

Week desired

ATP in desired week

Place order

1

500

4

250

Should not (since ATP < than demand)

2

500

5

200

Should not

(since ATP < than demand)

3

400

1

250

Should not

(since ATP < than demand)

4

400

7

250

Should not

(since ATP < than demand)

Add a comment
Know the answer?
Add Answer to:
Question 1 (2-Part) a) Complete the MPS record below for a single item. (Enter your responses as integers. A response of 0is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead T...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • I need the Mps quantity and MPS start % Problem 1 Questi Complete the MPS record...

    I need the Mps quantity and MPS start % Problem 1 Questi Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: week Quantity Week on Hand: 30 1 2 4 6 7 8 3 28 5 23 22 18 31 27 31 32 13 17 7 17 11 0 9 0 Forecast Customer orders (booked) Projected on-hand...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT