Qa.
Projected on-hand after MPS = Previous week Inventory + MPS – Week Requirements
Where, week requirement = maximum (forecast, Orders)
POH = beginning inv + MPS – maximum (Forecast, customer orders)
Before placing MPS if the POH is negative , then place order of 60 units in that week. Update the POH again after placing MPS order.
(for week 2, before MPS the POH = 17 – max(20,17) = -3, thus the MPS of Q = 60 is placed and POH is updated)
Order Policy = |
60 |
|||||||
Beginning Inventory = |
35 |
|||||||
Week 1 |
Week 2 |
Week 3 |
Week 4 |
Week 5 |
Week 6 |
Week 7 |
Week 8 |
|
Forecast |
18 |
20 |
28 |
28 |
21 |
30 |
36 |
35 |
Orders |
15 |
17 |
11 |
17 |
9 |
0 |
11 |
0 |
Projected On-Hand |
35-max(18,15) = 17 |
17+60- max(20,17) = 57 |
29 |
1 |
40 |
10 |
34 |
59 |
Master Production Schedule |
0 |
60 |
0 |
0 |
60 |
0 |
60 |
60 |
MPS Start |
60 |
0 |
0 |
60 |
0 |
60 |
60 |
0 |
Since the Lead time is 1 week, the MPs will start 1 week prior to MPS placed.
Qb.a
Projected on-hand after MPS = Previous week Inventory + MPS – Week Requirements
Where, week requirement = maximum (forecast, Orders)
POH = beginning inv + MPS – maximum (Forecast, customer orders)
Before placing MPS if the POH is negative , then place order of 60 units in that week. Update the POH again after placing MPS order.
(for week 2, before MPS the POH = 17 – max(20,17) = -3, thus the MPS of Q = 60 is placed and POH is updated)
Available to promise (ATP)
For first week: ATP = Beg. Inv + MPS for first week - sum of orders for weeks till next MPS is scheduled
For remaining week: ATP = MPS for a week - sum of orders for weeks till next MPS is scheduled
(the week in which MPS is not scheduled, the ATP will remain same as previous weeks)
Order Policy = |
500 |
||||||||||
Beginning Inventory = |
400 |
||||||||||
Week 1 |
Week 2 |
Week 3 |
Week 4 |
Week 5 |
Week 6 |
Week 7 |
Week 8 |
Week 9 |
Week 10 |
||
Forecast |
550 |
300 |
350 |
400 |
300 |
400 |
200 |
350 |
500 |
450 |
|
Orders |
300 |
350 |
250 |
250 |
200 |
100 |
150 |
100 |
150 |
100 |
|
Projected On-Hand |
400+500-Max(550,300) = 350 |
0 |
150 |
250 |
450 |
50 |
350 |
0 |
0 |
50 |
|
Master Production Schedule |
500 |
0 |
500 |
500 |
500 |
0 |
500 |
0 |
500 |
500 |
|
MPS Start |
500 |
0 |
500 |
500 |
500 |
0 |
500 |
0 |
500 |
||
Available-to-Promise |
400+500 -(300+350) = 250 |
500-(250) = 250 |
250 |
200 |
250 |
350 |
400 |
Qb.b
Order |
Quantity |
Week desired |
ATP in desired week |
Place order |
1 |
500 |
4 |
250 |
Should not (since ATP < than demand) |
2 |
500 |
5 |
200 |
Should not (since ATP < than demand) |
3 |
400 |
1 |
250 |
Should not (since ATP < than demand) |
4 |
400 |
7 |
250 |
Should not (since ATP < than demand) |
Question 1 (2-Part) a) Complete the MPS record below for a single item. (Enter your responses as integers. A response of 0is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead T...
I need the Mps quantity and MPS start % Problem 1 Questi Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: week Quantity Week on Hand: 30 1 2 4 6 7 8 3 28 5 23 22 18 31 27 31 32 13 17 7 17 11 0 9 0 Forecast Customer orders (booked) Projected on-hand...