I need the Mps quantity and MPS start
Important Note: You have placed the cursor right on the period-8 forecast. It is not visible clearly. I assume it to be 38. Check this.
If this is not 38, the entries will change.
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Forecast | 22 | 18 | 28 | 31 | 23 | 27 | 31 | 38 |
Customer orders | 13 | 17 | 7 | 17 | 11 | 0 | 9 | 0 |
Projected on-hand | 8 | 50 | 22 | 51 | 28 | 1 | 30 | 52 |
MPS Qty | 0 | 60 | 0 | 60 | 0 | 0 | 60 | 60 |
MPS start | 60 | 0 | 60 | 0 | 0 | 60 | 60 | 0 |
I need the Mps quantity and MPS start % Problem 1 Questi Complete the MPS record...
Question 1 (2-Part) a) Complete the MPS record below for a single item. (Enter your responses as integers. A response of 0is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: 1 week on Hand: 35 20 28 28 30 35 18 Customer orders 17 17 MPS quantity MPS start b) Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response...
Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30
1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...
Part II. TECHHICHI PPUDICMS (SHOW ALL CHICHI WUIS UIT Law Problem 7. (10%) Using the information in the following table, prepare a prospective MPS and calculate the available-to-promise quantities. The order policy is to produce in lots of 300. 1 100 40 2 100 190 3 100 220 Week 4 5 100 120 70 60 6 120 110 7 120 40 8 120 Quantity on hand: 100 Forecast Customer orders (CO) Projected on-hand inventory MPS quantity Available-to-promise (ATP) Assume that...
Show work Spring 2018 Name: LD. #: 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots of 100. Show all your calculations on the paper to receive full or partial credits. Week Quantity on hand: 40 1 Forecast 40|40|40|40|50 50 | 50 | 50 Customer orders (booked)20 95 40 45 15 75 20 10 Projected on-hand Inventory MPS...
needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...
i Data Table Table 2. INVENTORY RECORD DATA F G C Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts Beginning inventory L4L 3 weeks 0 150 (week 2) 125 D FOQ = 800 3 weeks 0 300 (week 2) 0 Item E FOQ = 600 4 weeks 0 600 (week 1) 255 L4L 2 weeks 70 None 670 L4L 1 week 0 1,200 (week 1) 0 Print Done Done nd then click Check Answer. Clear All The BOM...
complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs. Problem 1: MPS and ATP A partial table for end item B is provided below. Compute the MPS for item B and then the ATP values. Complete the table and then answer the multiple-choice questions: you need to complete the table to receive full credit (even if the answers to multiple-choice questions are correct). Item B Lead Time: 1 weeks Lot Size: 80 units...
The bill of materials and the data from the inventory records for product A are shown in the figure to the right. Assume that the MPS start quantities for A are 100 units in weeks 1, 2, and 7. Derive an MRP plan for the components going into product A using the data in the table below Item Data Category L4L 2 weeks 100 (week 2) 350 L4L 1 week None 215 Lot-sizing rule Lead time Scheduled receipts Beginning inventory...
Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank - be...