Assignment 8 is due on Sunday 8/2 at 11:00 AM Complete the following MPS record and find out what is the available-to-promise
0 0
Add a comment Improve this question Transcribed image text
Answer #1

А B D E TI G H 1 2 3 Period Forecast Orders POH 4 5 6 1 2 3 4 5 6 20 22 23 20 25 20 21 20 21 23 20 8 =C6+20-MAX(C3:04) =D6+C5

Period 1 2 3 4 5 6
Forecast 20 22 23 20 25 20
Orders 21 20 21 23 20 8
POH 49 27 4 31 6 36
MPS 50 0 0 50 0 50
ATP 8 7 42
Add a comment
Know the answer?
Add Answer to:
Assignment 8 is due on Sunday 8/2 at 11:00 AM Complete the following MPS record and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and...

    Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • Prepare a master production schedule for industrial pumps in the manner of the following ta Use...

    Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...

  • Using the following MPS record, what is the MPS start for week 7? MPS Lot Size...

    Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30

  • Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products,...

    Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Complete the following MPS time-phased record. Smell Fresh On Hand Week 1 2 3 4 5 6 7 8 Forecast 20 20 20 30 30 30 30 30 Orders 5 3 2 Projected available balance 20 50 30 10 30 50 20 40 10 Available to promise MPS 50 50 50 50 MPS Lot Size = 50 The following events...

  • Complete the following MPS record and find out what is the available-to-promise

    Q1. Complete the following MPS record and find out what is the available-to-promise. There are 10 units beginning inventory and the lot size is 65, Submit your answer in the drop box Q2. Given the following data, construct a material requirements plan for all components which will result in 200 units of (A) at the beginning of week 6. (Submit your answer in the drop box)

  • 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to-...

    1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...

  • complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs....

    complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs. Problem 1: MPS and ATP A partial table for end item B is provided below. Compute the MPS for item B and then the ATP values. Complete the table and then answer the multiple-choice questions: you need to complete the table to receive full credit (even if the answers to multiple-choice questions are correct). Item B Lead Time: 1 weeks Lot Size: 80 units...

  • Problem 8 1) Complete the Table below. 2) Based on the completed table what is the...

    Problem 8 1) Complete the Table below. 2) Based on the completed table what is the largest additional order that could be accepted for delivery for the end of week 8? please show your work so I can understand how to do it 1 P301 - Problem 8 21) Complete the Table below. 32) Based on the completed table what is the largest additional order that could be accepted for delivery for the end of week 8? ULUI Order Policy...

  • Refer to the Excel speadsheet, "Inventory Management," to complete the "Analytics Exercise: An MRP Explosion -...

    Refer to the Excel speadsheet, "Inventory Management," to complete the "Analytics Exercise: An MRP Explosion - Brunswick Motors," at the end of Chapter 21 in the textbook. Answer Questions 1-3. Given Spread Sheet: A-Topic 3 Part 1&2 AND  A-Topic 3 Part 3 Please use given information, show formulas/ calculations, and give reasons behind answer. Part 2 Gear Box Given Information Setu Invento Number of orders (count cells with values for planned order release Set-up Costs=# of Orders X Setup Costs 8...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT