Bonita Industries applies overhead on the basis of machine
hours. Given the following data, compute overhead applied and the
under- or overapplication of overhead for the period:
Estimated annual overhead cost | $1700000 |
Actual annual overhead cost | $1675000 |
Estimated machine hours | 500000 |
Actual machine hours | 490000 |
$1666000 applied and $9000 underapplied
$1675000 applied and neither under-nor overapplied
$1666000 applied and $9000 overapplied
$1700000 applied and $9000 overapplied
Option (a) is correct
First we will calculate the pre determined overhead rate as per below:
Pre determined overhead rate = Estimated overheads / Estimated machine hours
Putting the given values in the above formula, we get,
Pre determined overhead rate = $1700000 / 500000 = $3.4 per hour
Now, we will calculate overheads applied as per below:
Overheads applied = Pre determined overhead rate * Actual machine hours
Overheads applied = $3.4 * 490000 = $1666000
Actual overheads (given) = $1675000
Since actual overheads are more than applied overheads, so it is under appliedoverheads.
Now, we will calculate the amount for under applied overheads as per below:
Under applied overheads = Actual overheads - Applied overheads
Under applied overheads = $1675000 - $1666000 = $9000
Bonita Industries applies overhead on the basis of machine hours. Given the following data, compute overhead...
Grim Company applies overhead on the basis of machine hours. Given the following data, compute overhead applied and the under- or overapplication of overhead for the period: Estimated annual overhead cost $3,400,000 Actual annual overhead cost $3,370,000 Estimated machine hours 400,000 Actual machine hours 395,000 Question 5 options: $3,357,500 applied and $12,500 overapplied. $3,357,500 applied and $12,500 underapplied. $3,370,000 applied and neither under- nor overapplied. $3,400,000 applied and $12,500 overapplied. Thank you
Current Attempt in Progress Sheffield Corp, applies overhead on the basis of machine hours. Given the following data, compute overhead applied and the under or overapplication of overhead for the period: cost Estimated annual overhead $4300000 Actual annual overhead cost $4270000 Estimated machine hours 200000 Actual machine hours 195000 $4192500 applied and $77500 underapplied $4270000 applied and neither under nor overapplied $4300000 applied and $77500 overapplied $4192500 applied and $77500 overapplied
Multiple Choice Question 125 Marigold Corp. applies overhead on the basis of machine hours. Given the following data, compute overhead applied and the under-or overapplication of overhead for the period: Estimated annual overhead cost $1600000 Actual annual overhead cost $1575000 Estimated machine hours 200000 Actual machine hours 190000 $1600000 applied and $55000 overapplied $1520000 applied and $55000 underapplied $1575000 applied and neither under nor overapplied $1520000 applied and $55000 overapplied Click if you would like to Show Work for this...
skip 23,24,26 22. Hen Hao Professor Mullen, Inc applies overhead on the basis of machine hours. Given the following data, compute overhead applied and the under-or overapplication of overhead for the period: Estimated SS annual overhead cost $1,200,000 Actual SS annual overhead cost $1,155,000 Estimated machine hours 400,000 Actual machine hours 380,000 A) $1,140,000 applied and $15,000 overapplied B) $1,200,000 applied and $15,000 overapplied C) $1,140,000 applied and $15,000 underapplied D) $1,145,000 applied and neither under- nor overapplied 23. If...
21. Hen Hao Lao Shi Mullen, Inc developed the following data: Beginning work in process inventory (WIP) Direct materials used (DM) Actual overhead (OH) Overhead applied (est OH) Cost of goods manufactured (CGM) Ending work in process (WIP) Hen Hao Lao Shi Mullen, Inc's total manufacturing costs (TMC) for the period is A) $570,000. B) $540,000. C) $390,000. D) cannot be determined from the data provided. Page 5 $270,000 210,000 330,000 240,000 360,000 450,000 22. Hen Hao Professor Mullen, Inc...
lkerd Company applies overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $300,000 for the year, and machine usage is estimated at 125,000 hours. For the year, $322,000 of overhead costs are incurred and 130,000 hours are used. Instructions (a) Compute the manufacturing overhead rate for the year (b) What is the amount of under-or overapplied overhead at December 31? (c) Prepare the adjusting entry to assign the under- or overapplied overhead for...
Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. At the beginning of the year, the company estimated its total overhead cost to be $325,000 and machine hours to be 25,000. Actual manufacturing overhead and machine hours were $372,000 and 26,000, respectively. Required: 1. Compute the predetermined overhead rate. Predetermined Overhead Rate per Machine Hour 2. Compute applied manufacturing overhead. Applied Manufacturing Overhead 3. Compute over- or underapplied manufacturing overhead. Manufacturing Overhead
Blanket Corporation applies manufacturing overhead on the basis of direct labor hours. At the beginning of the most recent year, the company bases its predetermined overhead rate on the total estimated overhead of $450,000 and 75,000 estimated machine hours. Actual manufacturing overhead for the year amounted to $460,000 and actual machine hours were 80,000. Assuming that the entire amount of the underapplied or overapplied overhead is closed out to cost of goods sold, what would be the effect of the...
Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. At the beginning of the year, the company estimated its total overhead cost to be $325,000 and machine hours to be 25,000. Actual manufacturing overhead and machine hours were $372,000 and 26,000, respectively. Required: 1. Compute the predetermined overhead rate. per Machine Hour Predetermined Overhead Rate 2. Compute applied manufacturing overhead. Ma Overhe 3. Compute over-or underapplied manufacturing overhead.
Vaughn Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are estimated to total $282,464 for the year, and machine usage is estimated at 126,100 hours. For the year, $324,848 of overhead costs are incurred and 130,200 hours are used. a) Compute the manufacturing overhead rate for the year b) What is the amount of under or overapplied overhead at Dec 31? c) The adjustment to assign the under/over applied over to cost of...