Question

8.2 Make a clear and neat sketch of the network specified below using precedence notation. On the precedence diagram cal- cul
Label Duration ROO Must Follow Operations H.I FJK D.K EK MN N.o LOP QR
8.2: make it clear please
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Must bollow opuration colelewals IH Earliest I Late 140 |ракм Total Float(TP) start | Finish Start Finish = (Latestutistul) Atap bago ♡ B A Scanned with CamScannerThe critical path will be found along the path where the Total Flo Eno. Now from the table we can see total float is zno alon

Add a comment
Know the answer?
Add Answer to:
8.2: make it clear please 8.2 Make a clear and neat sketch of the network specified...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please help me with this question (( clear draw Please)) Draw the network diagram, including all...

    Please help me with this question (( clear draw Please)) Draw the network diagram, including all calculations of nodes using the following format: Early Start Duration Early Finish Task Name Late Sta rt Slack Late Finish List the networkpaths below: Determine the criticalpath(s). What is it and what is its duration? Activity Duration Dependency Start 0 A 6 Start B 1 A C 3 A,B D 5 A, B E 12 Start F 4 D, E G 2 C, F...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT