Question

Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.25 $2.10 Raw materials units 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours 14,400 15,000 Manufacturing overhead incurred $189,500 Manufacturing overhead applied $193,500 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $55,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per machine hour $1.30 Overhead is applied on the basis of standard machine hours. 3.00 hours of machine time are required for each direct labor hour. The jobs were sold for $400,000. Selling and administrative expenses were $40,000. Assume that the amount of raw materials purchased equaled the amount used. Compute all of the variances for (1) direct materials and (2) direct labor. (Round per unit values to 2 decimal places, e.g. 52.75 and final answers to 0 decimal places, e.g. 52.) (1) Total materials variance $ Materials price variance $ Materials quantity variance $ (2) Total labor variance $ Labor price variance $ Labor quantity variance $ Compute the total overhead variance. Total overhead variance $ Prepare an income statement for management. (Ignore income taxes.) (Round per unit values to 2 decimal places, e.g. 52.75 and final answers to 0 decimal places, e.g. 52.) AYALA CORPORATION Income Statement $ $ $

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:-

As for HomeworkLib policy we wrote only some sub parts

Standard Actual
Particulars Units Price Total Units Price Total
Materials                                                  10,000.00                                                              2.10      21,000.00                          10,600.00                      2.25                            23,850.00
Labor                                                  15,000.00                                                              8.00    120,000.00                          14,400.00                  8.4000                         120,960.00
   141,000.00                         144,810.00
Total Material Variance =   Standard Material Cost - Actual Material Cost
Total Material Variance =   21,000 - 23,850
Total Material Variance =   2,850 Unfavourable
Material Price Variance (Standard Price - Actual Price)*Actual Quantity
Material Price Variance (2.10 - 2.25) 10,600
Material Price Variance 1,590 Adverse
Material Quantity Variance (Standard Qty - Actual Qty)*Standard Price
Material Quantity Variance (10,000 - 10,600)2.10
Material Quantity Variance 1,260 Unfavourable
Total Labor Variance =   Standard Labor Cost - Actual Labor Cost
Total Labor Variance =   120,000-120,960
Total Labor Variance =   960 Unfavourable
Labor Rate Variance (Standard Rate - Actual Rate)*Actual hours  
Labor Rate Variance (8-8.40)14,400
Labor Rate Variance 5,760 Unfavourable
Labor Quantity Variance (Standard hrs - Actual hrs)*Standard Rate
Labor Quantity Variance (15,000-14,400)8
Labor Quantity Variance 4,800 Favourable

if you have any query please ask me in comment box i am here to helps you don't give direct Thumbs down.if you satisfied my work give Thumbs UP

******THANK YOU*******

Add a comment
Know the answer?
Add Answer to:
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...

    Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Raw materials unit cost Raw materials units Direct labor payroll Direct labor hours Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual $2.20 11,300 $166,500 15,000 $210,420 Standard $2.10 10,900 $159,600 15,200...

  • Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...

    Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual $2.30 11,400 $157,940 14,900 $223,276 Standard $2.15 10,500 $153,520 15,200 Raw materials unit cost Raw materials units Direct labor payroll Direct labor hours Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 Costs and Production Data Raw materials unit cost Raw materials units used Direct labor payroll Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual Standard $2.10 $1.90 11,300 10,700 $175,500 $171,360 15.000 15.300 $212,930...

  • Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...

    Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard $2.10 11,400 $169,860 14,900 $211,720 $2.00 11,000 $165,680 15,200 Raw materials unit cost Raw materials units Direct labor payroll Direct labor hours Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.20 $2.00 Raw materials units used 11,200 10,300 Direct labor payroll $175,820 $169,830 Direct labor hours worked 14,900 15,300 Manufacturing overhead incurred $202,750 Manufacturing overhead applied $206,550 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.10 $1.90 Raw materials units used 11,300 10,700 Direct labor payroll $175,500 $171,360 Direct labor hours worked 15,000 15,300 Manufacturing overhead incurred $212,930 Manufacturing overhead applied $215,730 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 15,200 Direct labor hours 14,800 $202.600 Manufacturing overhead incurred $205,200 Manufacturing overhead applied Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 Direct labor hours 14,800 15,200 Manufacturing overhead incurred $202,600 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Het Announcements CALCULATO R Problem 11-2A (Video) Ayala Corporation accumulates the following data relative to jobs...

    Het Announcements CALCULATO R Problem 11-2A (Video) Ayala Corporation accumulates the following data relative to jobs started and "inished during the month of June 2020. Cests and Production Data Actual Standard 11.000 SIGN 16.60 211.720 acturing overhead oled 5214320 573.950 Overhead is applied on the basis of standard machine hours. 3.00 hours of machine time are required for each direct labor hour. The jobs were sold for $487,000. Selling and administrative expenses were $39,300. Assume that amount of raw materials...

  • Actual Costs and Production Data Standard $2.25 $2.10 Raw materials unit cost Raw materials units 10,600...

    Actual Costs and Production Data Standard $2.25 $2.10 Raw materials unit cost Raw materials units 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours 15,000 14,400 $189,500 Manufacturing overhead incurred $193,500 Manufacturing overhead applied Machine hours expected to be used at normal capacity 42,500 $55,250 Budgeted fixed overhead for June $3.00 Variable overhead rate per machine hour $1.30 Fixed overhead rate per machine hour Overhead is applied on the basis of standard machine hours. 3.00 hours of machine time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT