Question

Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020.

Costs and Production Data

Actual

Standard

Raw materials unit cost $2.30 $2.20
Raw materials units 11,100 10,300
Direct labor payroll $170,200 $164,160
Direct labor hours 14,800 15,200
Manufacturing overhead incurred $202,600
Manufacturing overhead applied $205,200
Machine hours expected to be used at normal capacity 43,500
Budgeted fixed overhead for June $65,250
Variable overhead rate per machine hour $3.00
Fixed overhead rate per machine hour $1.50

Overhead is applied on the basis of standard machine hours. 3.00 hours of machine time are required for each direct labor hour. The jobs were sold for $460,000. Selling and administrative expenses were $42,100. Assume that the amount of raw materials purchased equaled the amount used.

Compute all of the variances for (1) direct materials and (2) direct labor. (Round per unit values to 2 decimal places, e.g. 52.75 and final answers to 0 decimal places, e.g. 52.)

(1) Total materials variance $

FavorableUnfavorableNeither favorable nor unfavorable

Materials price variance $

FavorableUnfavorableNeither favorable nor unfavorable

Materials quantity variance $

FavorableUnfavorableNeither favorable nor unfavorable

(2) Total labor variance $

FavorableUnfavorableNeither favorable nor unfavorable

Labor price variance $

FavorableUnfavorableNeither favorable nor unfavorable

Labor quantity variance $

FavorableUnfavorableNeither favorable nor unfavorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution

Total Material Variance $           2,870.00 Unfavourable-U
Material Price Variance $           1,110.00 Unfavourable-U
Material quantity variance $           1,760.00 Unfavourable-U
Total Labor variance $           6,040.00 Unfavourable-U
Labor rate variance   $         10,360.00 Unfavourable-U
Labor Efficiency variance $           4,320.00 Favourable-F

Working

Material Price Variance
( Standard Rate - Actual Rate ) x Actual Quantity
( $                    2.20 - $                     2.30 ) x 11100
-1110
Variance $             1,110.00 Unfavourable-U
Material Quantity Variance
( Standard Quantity - Actual Quantity ) x Standard Rate
( 10300 - 11100 ) x $              2.20
-1760
Variance $             1,760.00 Unfavourable-U
Material Spending Variance
( Standard Cost - Actual Cost )
( $         22,660.00 - $           25,530.00 )
-2870
Variance $             2,870.00 Unfavourable-U

.

Labor Rate Variance
( Standard Rate - Actual Rate ) x Actual Labor Hours
( $                  10.80 - $                   11.50 ) x 14800
-10360
Variance $           10,360.00 Unfavourable-U
Labour Efficiency Variance
( Standard Hours - Actual Hours ) x Standard Rate
( 15200 - 14800 ) x $           10.80
4320
Variance $             4,320.00 Favourable-F
Labor Spending Variance
( Standard Cost - Actual Cost )
( $       164,160.00 - $        170,200.00 )
-6040
Variance $             6,040.00 Unfavourable-U
Add a comment
Know the answer?
Add Answer to:
Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 Direct labor hours 14,800 15,200 Manufacturing overhead incurred $202,600 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.20 $2.00 Raw materials units used 11,200 10,300 Direct labor payroll $175,820 $169,830 Direct labor hours worked 14,900 15,300 Manufacturing overhead incurred $202,750 Manufacturing overhead applied $206,550 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 15,200 Direct labor hours 14,800 $202.600 Manufacturing overhead incurred $205,200 Manufacturing overhead applied Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.10 $1.90 Raw materials units used 11,300 10,700 Direct labor payroll $175,500 $171,360 Direct labor hours worked 15,000 15,300 Manufacturing overhead incurred $212,930 Manufacturing overhead applied $215,730 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Ayala Corporation accumulates the following data... Please explain answers?

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020.Costs and Production DataActualStandardRaw materials unit cost$2.30$2.20Raw materials units11,10010,300Direct labor payroll$170,200$164,160Direct labor hours14,80015,200Manufacturing overhead incurred$202,600Manufacturing overhead applied$205,200Machine hours expected to be used at normal capacity43,500Budgeted fixed overhead for June$65,250Variable overhead rate per machine hour$3.00Fixed overhead rate per machine hour$1.50Overhead is applied on the basis of standard machine hours. 3.00 hours of machine time are required for each direct labor hour. The jobs were sold for...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 Costs and Production Data Raw materials unit cost Raw materials units used Direct labor payroll Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual Standard $2.10 $1.90 11,300 10,700 $175,500 $171,360 15.000 15.300 $212,930...

  • Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...

    Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard $2.10 11,400 $169,860 14,900 $211,720 $2.00 11,000 $165,680 15,200 Raw materials unit cost Raw materials units Direct labor payroll Direct labor hours Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.25 $2.10 Raw materials units 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours 14,400 15,000 Manufacturing overhead incurred $189,500 Manufacturing overhead applied $193,500 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $55,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Concord Corporation accumulates the following data relative to jobs started and finished during the month of June 2020....

    Concord Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.40 $2.20 Raw materials units 11,000 10,300 Direct labor payroll $162,800 $159,600 Direct labor hours 14,800 15,200 Manufacturing overhead incurred $217,464 Manufacturing overhead applied $221,464 Machine hours expected to be used at normal capacity 41,500 Budgeted fixed overhead for June $66,400 Variable overhead rate per machine hour $3.10 Fixed overhead rate per...

  • Problem 25-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and...

    Problem 25-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 Actual Costs and Production Data Raw materials unit cost Raw materials units used 11,000 $162,0DO 14,800 $203,200 Standard $1.90 10,500 $159,500 15,200 Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Foced overhead rate per machine...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT