Concord Corporation accumulates the following data relative to jobs started and finished during the month of June 2020.

Costs and Production Data

Actual

Standard

Raw materials unit cost $2.40 $2.20
Raw materials units 11,000 10,300
Direct labor payroll $162,800 $159,600
Direct labor hours 14,800 15,200
Manufacturing overhead incurred $217,464
Manufacturing overhead applied $221,464
Machine hours expected to be used at normal capacity 41,500
Budgeted fixed overhead for June $66,400
Variable overhead rate per machine hour $3.10
Fixed overhead rate per machine hour $1.60


Overhead is applied on the basis of standard machine hours. 3.10 hours of machine time are required for each direct labor hour. The jobs were sold for $478,000. Selling and administrative expenses were $37,900. Assume that the amount of raw materials purchased equaled the amount used.

prepare an income statement for management. (Ignore income taxes



CONCORD CORPORATION Income Statement For the Month Ended June 30, 2020 Sales Revenue 478000 Cost of Goods Sold 403724 Gross P
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The gross profit actual will be

= gross profit at standard - total variance unfavorable

= 74276 - 2940

= $ 71336

Net profit = gross profit actual- selling and administrative expenses

=71336 - 37900

= $ 33436

Add a comment
Know the answer?
Add Answer to:
Concord Corporation accumulates the following data relative to jobs started and finished during the month of June 2020....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and...

    Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.40 $2.20 Raw materials units used 11,000 10,300 Direct labor payroll $162,800 $159,600 Direct labor hours worked 14,800 15,200 Manufacturing overhead incurred $217,464 Manufacturing overhead applied $221,464 Machine hours expected to be used at normal capacity 41,500 Budgeted fixed overhead for June $66,400 Variable overhead rate per...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.20 $2.00 Raw materials units used 11,200 10,300 Direct labor payroll $175,820 $169,830 Direct labor hours worked 14,900 15,300 Manufacturing overhead incurred $202,750 Manufacturing overhead applied $206,550 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 Costs and Production Data Raw materials unit cost Raw materials units used Direct labor payroll Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual Standard $2.10 $1.90 11,300 10,700 $175,500 $171,360 15.000 15.300 $212,930...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 Direct labor hours 14,800 15,200 Manufacturing overhead incurred $202,600 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.10 $1.90 Raw materials units used 11,300 10,700 Direct labor payroll $175,500 $171,360 Direct labor hours worked 15,000 15,300 Manufacturing overhead incurred $212,930 Manufacturing overhead applied $215,730 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.25 $2.10 Raw materials units 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours 14,400 15,000 Manufacturing overhead incurred $189,500 Manufacturing overhead applied $193,500 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $55,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...

    Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard $2.10 11,400 $169,860 14,900 $211,720 $2.00 11,000 $165,680 15,200 Raw materials unit cost Raw materials units Direct labor payroll Direct labor hours Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 15,200 Direct labor hours 14,800 $202.600 Manufacturing overhead incurred $205,200 Manufacturing overhead applied Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of...

    Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.15 Raw materials units used 11,400 10,500 Direct labor payroll $172,840 $168,720 Direct labor hours worked 14,900 15,200 Manufacturing overhead incurred $223,276 Manufacturing overhead applied $226,176 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.10 Fixed overhead...

  • Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of...

    Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.15 Raw materials units used 11,400 10,500 Direct labor payroll $172,840 $168,720 Direct labor hours worked 14,900 15,200 Manufacturing overhead incurred $223,276 Manufacturing overhead applied $226,176 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.10 Fixed overhead...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT