The ANSWERS above for my problems are correct. I need someone to please show work for them so I can understand how to do them! Thanks!
Mean lead time demand for BX-5 = 65
The standard deviation of demand = 8
Desired service level = 90%
Z-value for achieving 90% service level = 1.28
Ans a)
Safety stock = Z * Standard deviation of demand
= 1.28 * 8
= 10.24 or 10 units
Ans b)
Appropriate re-order point = Mean lead time demand + Safety stock
= 65 + 10
= 75 units
The ANSWERS above for my problems are correct. I need someone to please show work for...
Linda L. is in charge of maintaining hospital supplies at General Hospital. During the past year the lead-time when ordering the BX-5 bandage was six weeks. Monthly (four weeks) mean demand was 300 and monthly standard deviation of the demand was 27 units. What is the reorder point needed to maintain a cycle service level of 99%? NORMINV(.99,300,27) NORMINV(.99,300*4/6, 27*4/6) NORMINV(.99, 300*6/4,27*6/4) d. None of the above
1. Linda L. is in charge of maintaining hospital supplies at General Hospital. During the past year the lead-time when ordering the BX-5 bandage was six weeks. Monthly (four weeks) mean demand was 300 and monthly standard deviation of the demand was 27 units. 1.1 What is the reorder point needed to maintain a cycle service level of 99%? a. NORMINV(.99,300,27) b. NORMINV(.99,300*4/6, 27*4/6) C. NORMINV(.99, 300*6/4,27*6/4) d. None of the above 1.2 Note the additional information: It costs $1.50...
Demand during lead time for one brand of TV is normally distributed with a mean of 36 TVs and a standard deviation of 15 TVs. What safety stock should be carried for 90% service level? What is the appropriate reorder point? Click the icon to view the normal table What safety stock should be carried for a 90% service level? Safety stock units (round your response to the nearest whole number).
Based on available information, lead time demand for PC jump drives averages 53 units (normally distributed), with a standard deviation of 5 drives. Management wants a 95% service level. Refer to the standard normal table for z-values. a) What value of Z should be applied? (1.04/1.28/2.06/1.65) b) How many drives should be carried as safety stock? __________ units (round your response to the nearest whole number). c) What is the appropriate reorder point? __________ units (round your response to the...
M7_IND5. Peter Sagan is in charge of maintaining hospital supplies at Champs Hospital. During the past year the mean weekly demand for a special type of tubing was 186 packages of this tubing with a standard deviation of 13 packages of tubing. The lead time for receiving this tubing from the supplier is 1.5 weeks. Peter would like to maintain a 95% service level and places an order for 750 packages every time an order is placed. a) How much...
Average daily demand (d) 130 cases Demand Standard deviation (σd) 20 cases Service level 94.0% Service level alternative 86.0% Lead tme, LT 6 days 1. What is the standard deviation of demand during lead time? Round your answer to one decimal place. _______ cases 2. What is the required safety stock at a 94 percent service level? Round your answer to the nearest whole number. _______ cases 3. What is the reorder point? Round your answer to the nearest whole...
HELP! PLEASE Petromax Enterprises uses a continuous review inventory control system for one of its SKUs. The following information is available on the item. The firm operates 52 weeks in a year. Demand = 91,000units/year Ordering cost = $32.50 Holding cost = $3.50/unit/year Average lead time = 4 Weeks Standard deviation of weekly demand = 250 units a. The economic order quantity for this item is ____units. (Enter your response rounded to the nearest whole number.) b. If Petromax wants...
Linda L. is in charge of maintaining hospital supplies at General Hospital. During the past year the lead-time when ordering the BX-5 bandage was six weeks. Monthly (four weeks) mean demand was 300 and monthly standard deviation of the demand was 27 units. Note the additional information: It costs $1.50 to hold such a bandage in stock for a year. The supplier is offering Linda to shorten the lead-time from 6 weeks to 3 weeks but the unit cost will...
Chicago's Hard Rock Hotel distributes a mean of 1,200 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 95 towels per day, based on occupancy. The laundry firm that has the linen contract requires a 4-day lead time. The hotel expects a 99% service level to satisfy high guest expectations. Refer to the standard normal table for z-values. a) What is the reorder point? ___towels (round...
High Tech Inc. is a virtual store that stocks a variety of calculators in its warehouse. Customer orders are placed; the orders are picked and packaged; and then orders are shipped to the customers. A fixed-order-quantity inventory control system (FQS) helps monitor and control these SKUs. The following information is for one of the calculators that High Tech stocks, sells, and ships. Average demand 9.5 calculators per week Lead time 5 weeks Order cost $15/order Unit cost $10.00 Carrying charge...