Hello, please answer this question regarding Microsoft Project 2016. Thank you
1. What are the new features of Project 2016 and How do you create
a WBS in Project 2016?
2. How do you enter task durations and establish dependencies between tasks?
3.How can you make sure that resource assignments do not mess up
your schedule?
4. How can you use the Team Planner to assign resources and reduce
overallocations?
5. How do you establish a baseline in Project 2016 and enter actual
information?
6. What type of information do you see in the Earned Value
table?
7. How can you copy a Timeline from Project into other applications
and access other application
files from within Project 2016?
8. Where can you access apps created for Project 2016?
1) i) New features of MS project 2016:
ii) Creating WBS:
Work breakdown structure (WBS) could be created by the following manner:
Project Code Prefix box could be preferred to create the project-specific code. Numbers, alphabets and symbols could be employed.
2) Task duration:
To establish task dependencies:
3) Assigning resources:
The way to stop the messing of schedule with the resource assignment is to assign the resources according to the resource calendar and provide accurate scheduling.
4) Team Planner:
5).Setting a baseline
Go to view tab and select Gnart chart which allows to set baseline for particular sub-tasks in a project. Instead if you want to create baseline for full project, then select the project tab and set the baseline.
6). Earned value
In order to evaluate the performance of cost, work schedule, we employ earned value. Another added advantage by employing earned value is that it enables comparison of actual values and baseline values. Generally, the earned value is based on the percentage of tasks completed and predicts the costs based on the baseline. Till the status date, the cost is calculated.
7).Copying the Time-line to other applications
You can do this by selecting the time-line tools format tab available under the timeline area. Now , you can select any other applications in the copy timeline group But in-order to employ this feature, you have to make sure that timeline is visible.
8).Accessing apps
You can access apps by employing web Office Add-ins by selecting store after clicking project. This takes you to alll necessary apps for creating a project.
Hello, please answer this question regarding Microsoft Project 2016. Thank you 1. What are the new...
You could consider each week of a course as a small project. It requires you to study some learning resources, participate in a discussion, and possibly complete a paper or a test. Create a work breakdown structure (WBS) that represents your projects for this week. Document the tasks you were asked to perform in this week of the course (you can use the list above as a starting point). Decompose each main task into subtasks that can be completed in...
In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software application that you have selected. Prepare the WBS, and submit the file to your instructor. This assignment is due Sunday at 11:59 p.m. All assignments should be uploaded in the Assignment area. Project Software Options There are many project management software applications that are designed to help develop project plans and schedules as well as keeping track of these plans and creating...
Microsoft PowerPoint 2016 has many new and improved features. What do you think is the most beneficial feature in PowerPoint 2016? Explain why and give a brief description of how this might help you.
Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...
Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...
Please Answer all these. Those questions are from New Perspectives Microsoft Office 365 & Excel 2016 . Need answers from Excel concern : 1. What formula would you enter to add the values in cells C1, C2, and C3? What function would you enter to achieve the same result? 2. What formula would you enter to count how many numeric values are in the range D21:D72? 3. If you insert cells into the range C1:D10, shifting the cells to the...
al Industries are likely to use 4 At Webster University, where you work as a project manager, you have been asked to conduct user training sessions for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): . First, confirm arrangements for the training facility you plan to use (2 days). • After you have confirmed the training facility, two tasks can begin at the same time:...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Analytics Exercise 4-2 You work for Microsoft in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Exhibit 5.13. It...
Hello, please help to identify the right answer choice of these questions. Thank you. ***755. A male adult is admitted because of an acetaminophen overdose. After transfer to the mental health unit, the client is told he has liver damage. Which information is most important for the nurse to include in the client's discharge plan? A. Avoid exposure to large crowds B. Do not take any over-the-counter medications C. Call the crisis hot line if feeling lonely D. Eat a...