Question

Hello, please answer this question regarding Microsoft Project 2016. Thank you 1. What are the new...

Hello, please answer this question regarding Microsoft Project 2016. Thank you


1. What are the new features of Project 2016 and How do you create a WBS in Project 2016?

2. How do you enter task durations and establish dependencies between tasks?

3.How can you make sure that resource assignments do not mess up your schedule?
4. How can you use the Team Planner to assign resources and reduce overallocations?
5. How do you establish a baseline in Project 2016 and enter actual information?
6. What type of information do you see in the Earned Value table?
7. How can you copy a Timeline from Project into other applications and access other application
files from within Project 2016?
8. Where can you access apps created for Project 2016?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) i) New features of MS project 2016:

  • Tell Me: This will look for the solution that we require instead of searching it online
  • Add-ins: Microsoft partners applications could be downloaded from the office store in the same efficient manner that could be very easy to integrate with the project
  • New Themes: Helps in changing the theme of the project.
  • Multiple Timeline view: Helps in visualizing different phases of the project plan.
  • Resource Capacity Heat Maps: Helps us to view how the resources are used effectively.
  • In-App Feedback: Provides the feedback directly

ii) Creating WBS:

Work breakdown structure (WBS) could be created by the following manner:

  • Click View-> pick a sheet view either a Task Sheet or Resource Sheet.
  • Click Project-> Go to Properties group.
  • Click WBS -> Define Code.

Project Code Prefix box could be preferred to create the project-specific code. Numbers, alphabets and symbols could be employed.

2) Task duration:

  • Click View -> Gantt Chart.
  • Now go to the Duration column and type the duration either in minutes (m), hours (h), days (d), weeks (w), or months (mo).
  • Press Enter.

To establish task dependencies:

  • Click View -> Gantt Chart.
  • Click on the Predecessors or Successors column and choose the cell that has to be linked with the task
  • The task that we require should be found from the hierarchical list of our task and choose the check box followed by clicking outside the drop-down box

3) Assigning resources:

The way to stop the messing of schedule with the resource assignment is to assign the resources according to the resource calendar and provide accurate scheduling.

  • For assigning the resources, click the Resource tab -> Assign Resources.

4) Team Planner:

  • To view Team planner, click the View tab on the ribbon
  • Click Team Planner from the Resource Views group (on the left side all the resource name with the unassigned start date and deadline will be seen and at the right the assigned resources will appear. Unallocated resources will appear on the bottom)

5).Setting a baseline

Go to view tab and select Gnart chart which allows to set baseline for particular sub-tasks in a project. Instead if you want to create baseline for full project, then select the project tab and set the baseline.

6). Earned value

In order to evaluate the performance of cost, work schedule, we employ earned value. Another added advantage by employing earned value is that it enables comparison of actual values and baseline values. Generally, the earned value is based on the percentage of tasks completed and predicts the costs based on the baseline. Till the status date, the cost is calculated.

7).Copying the Time-line to other applications

You can do this by selecting the time-line tools format tab available under the timeline area. Now , you can select any other applications in the copy timeline group But in-order to employ this feature, you have to make sure that timeline is visible.

8).Accessing apps

You can access apps by employing web Office Add-ins by selecting store after clicking project. This takes you to alll necessary apps for creating a project.

Add a comment
Know the answer?
Add Answer to:
Hello, please answer this question regarding Microsoft Project 2016. Thank you 1. What are the new...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT