Work In Process Inventory | |||||
1-Jun | Beginning Bal | $5,928 | 30th June | Finished Goods Inventory | $15,772 |
Raw Material Inventory | 5243 | ||||
Direct Material | 3852 | ||||
Manufacturing overhead (3852*1.25) | 4815 | ||||
30-Jun | Ending Balance | $4,066 | |||
working | |||||
Finished Goods Inventory | |||||
Beginning Bal | $5,928 | ||||
Direct material | |||||
Rodgers | 1177 | ||||
Stevens | 535 | ||||
Linton | 1391 | ||||
Direct Labor | |||||
Rodgers | 1327 | ||||
Stevens | 385 | ||||
Linton | 1284 | ||||
manufacturing overhead | 3745 | ||||
(1327+385+1284)*1.25 | |||||
Total | $15,772 | ||||
If any doubt please comment |
Problem 15-3A (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory 4,494 Manufacturing Overhead Applied $34,925 Work in Process Inventory $5,928 Manufacturing Overhead Incurred $33,866 Subsidiary data for Work in Process Inventory on June 1 are as follows. ob Cost Sheets Customer Job Cost Element Direct materials Direct labor Rodgers...
Work in process inventory balance Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory 4,494 Manufacturing Overhead Applied $34,925 Work in Process Inventory $5,928 Manufacturing Overhead Incurred $33,866 Subsidiary data for Work in Process Inventory on June 1 are as follows. ob Cost Sheets Customer Job Cost Element...
What is the correct finished goods inventory and cost of goods sold when the jobs are completed? Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory 4,494 Manufacturing Overhead Applied $34,925 Work in Process Inventory $5,928 Manufacturing Overhead Incurred $33,866 Subsidiary data for Work in Process Inventory on...
Problem 15-3A (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,620 Manufacturing Overhead Applied $35,904 Work in Process Inventory $6,095 Manufacturing Overhead Incurred $34,815 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element...
Problem 15-3A (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,872 Manufacturing Overhead Applied $37,862 Work in Process Inventory $6,426 Manufacturing Overhead Incurred $36,714 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element...
Problem 15-3A (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data, Raw Materials Inventory Work in Process Inventory $5,208 Manufacturing Overhead Applied $6,870 Manufacturing Overhead Incurred $40,474 $39,246 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Rodgers Stevens...
Problem 15-3A (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work in Process Inventory $4,284 $5,652 Manufacturing Overhead Applied Manufacturing Overhead Incurred $33,293 $32,283 Subsidiary data for Work in Process Inventory on June 1 are as follows. Cost Element Direct materials Direct labor Manufacturing...
Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $3,900 Manufacturing Overhead Applied $35,600 Work in Process Inventory $5,975 Manufacturing Overhead Incurred $29,400 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element...
Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work in Process Inventory $3,900 $5,975 Manufacturing Overhead Applied Manufacturing Overhead Incurred $35,600 $29,400 Subsidiary data for Work in Process Inventory on June 1 are as follows. Cost Element Direct materials Direct labor...
*Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work in Process Inventory $4,200 Manufacturing Overhead Applied $5,450 Manufacturing Overhead Incurred $30,300 $30,200 Subsidiary data for Work in Process Inventory on June 1 are as follows. Cost Element Direct materials Direct labor...