Capacity of machine = 1170 parts per day

Total daily demand = Black + Grey + Tan demand = 500 + 145 + 195 = 840 parts per day

Utilization = Total daily demand/Capacity per day*100 = 840/1170*100 = 71.79%

Ans 71.79%

Add a comment
Know the answer?
Add Answer to:
Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 545 units/day Grey: 130 units/day Tan: 210 units/day The injection-molding machine can produce a total of 1,125 parts per day. What is the utilization of machine from these three parts as a percentage?

  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 490 units/day Grey: 145 units/day Tan: 185 units/day The injection-molding machine can produce a total of 1,055 parts per day running 24 hours per day. If Plainwell is going to produce the parts using a cyclic schedule and it takes 2 hours to change from one color to the next,...

  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 480 units/day Grey: 140 units/day Tan: 180 units/day The injection-molding machine can produce a total of 1,135 parts per day running 24 hours per day. If Plainwell is going to produce the parts using a cyclic schedule and it takes 2 hours to change from one color to the next,...

  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 530 units/day Grey: 135 units/day Tan: 185 units/day The injection-molding machine can produce a total of 1,010 parts per day running 24 hours per day. It costs Plainwell $1,110 to set up each color for producition and the daily holding cost for each part is $0.03. What is the length...

  • Question 7 (4 points) Plainwell Polymers is going to producing the main dashboard structure for a...

    Question 7 (4 points) Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 415 units/day Grey: 115 units/day Tan: 180 units/day The injection-molding machine can produce a total of 950 parts per day running 24 hours per day. It costs Plainwell $1,100 to set up each color for producition and the daily holding cost for each part is $0.04....

  • Why did the Energy Telematics project fail and why was Joel's tram vaught off guard by...

    Why did the Energy Telematics project fail and why was Joel's tram vaught off guard by the hostile reaction of the truck drivers at the Omaha depot? MINI CASE Working Smarter at Continental Furniture International Joel Parsons hurried down the hall to the monthly executive committee meeting doing a mental checklist of all the things he was responsible for: sales analysis-check; mar keting stats-check; quarterly and YTD financials-check; operating statistics-check trends in each of these areas-check. Parsons was right hand...

  • 4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit go...

    4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit going forward? 5. Analyze the company’s financial performance. Do trends suggest that Fitbit’s strategy is working? 6.What recommendations would you make to Fitbit management to address the most important strategic issues facing the company? Fitbit, Inc., in 2017: Can Revive Its Strategy and It Reverse Mounting Losses? connect ROCHELLE R. BRUNSON Baylor University MARLENE M. REED Baylor University in the...

  • SYNOPSIS The product manager for coffee development at Kraft Canada must decide whether to introduce the...

    SYNOPSIS The product manager for coffee development at Kraft Canada must decide whether to introduce the company's new line of single-serve coffee pods or to await results from the product's launch in the United States. Key strategic decisions include choosing the target market to focus on and determining the value proposition to emphasize. Important questions are also raised in regard to how the new product should be branded, the flavors to offer, whether Kraft should use traditional distribution channels or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT