Question

Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows:

Black: 480 units/day

Grey: 140 units/day

Tan: 180 units/day

The injection-molding machine can produce a total of 1,135 parts per day running 24 hours per day. If Plainwell is going to produce the parts using a cyclic schedule and it takes 2 hours to change from one color to the next, what is the minimum cycle time for the cyclic schedule in hours?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per Instruction, Plainwell Polymers is going to make the parts using cyclic schedule and given data is that it takes 2 hours to change from one color to the next, so, here cycle will include --- Black color – changing time – Grey Color – Changing time – Tan Color – Changing Time and move to Black color,

Again, 1 day = 24 hours, for Black = 24 Hours / 480 Units = 0.05 Hours per unit, For Grey = 24 hours/140 Units = 0.17 hours/unit, for Tan 24 Hours/180 units = 0.13 hours per unit,

Minimum cycle time for the cyclic schedule in hours = 0.05 Hours + 2 Hours + 0.17 hours + 2 Hours + 0.13 hours + 2 Hours = 6.35 hours

Add a comment
Know the answer?
Add Answer to:
Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 490 units/day Grey: 145 units/day Tan: 185 units/day The injection-molding machine can produce a total of 1,055 parts per day running 24 hours per day. If Plainwell is going to produce the parts using a cyclic schedule and it takes 2 hours to change from one color to the next,...

  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 530 units/day Grey: 135 units/day Tan: 185 units/day The injection-molding machine can produce a total of 1,010 parts per day running 24 hours per day. It costs Plainwell $1,110 to set up each color for producition and the daily holding cost for each part is $0.03. What is the length...

  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 500 units/day Grey: 145 units/day Tan: 195 units/day The injection-molding machine can produce a total of 1,170 parts per day. What is the utilization of machine from these three parts as a percentage?

  • Plainwell Polymers is going to producing the main dashboard structure for a new car design. The...

    Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 545 units/day Grey: 130 units/day Tan: 210 units/day The injection-molding machine can produce a total of 1,125 parts per day. What is the utilization of machine from these three parts as a percentage?

  • Question 7 (4 points) Plainwell Polymers is going to producing the main dashboard structure for a...

    Question 7 (4 points) Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 415 units/day Grey: 115 units/day Tan: 180 units/day The injection-molding machine can produce a total of 950 parts per day running 24 hours per day. It costs Plainwell $1,100 to set up each color for producition and the daily holding cost for each part is $0.04....

  • Should World Kitchen outsource Pyrex production and close the Charleroi plant? If so, how many suppliers should the company employ and where should they be located? We were una...

    Should World Kitchen outsource Pyrex production and close the Charleroi plant? If so, how many suppliers should the company employ and where should they be located? We were unable to transcribe this imagedishwas resulted from a process that pressed together yers of thin, strengthened opaque glass. products if they were moved overseas and simply source the lower-cost private-label versions directly sales and marketing functions. THE MARKET Givsn its extensive experience with outsourcing the Giobal Sourcing Department at World Kitchen had...

  • 4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit go...

    4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit going forward? 5. Analyze the company’s financial performance. Do trends suggest that Fitbit’s strategy is working? 6.What recommendations would you make to Fitbit management to address the most important strategic issues facing the company? Fitbit, Inc., in 2017: Can Revive Its Strategy and It Reverse Mounting Losses? connect ROCHELLE R. BRUNSON Baylor University MARLENE M. REED Baylor University in the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT