A project has the following cash flows:
Year | Cash Flows |
0 | -15000 |
1 | 6630 |
2 | 7971 |
3 | 6730 |
What is the NPV at a discount rate of zero percent? (Round your final answer to the nearest dollar amount. Omit the "$" sign and commas in your response. For example, $123,456.78 should be entered as 123457.)
Answer:
CF=Cash flow
r= discount rate =0%
t=time in which cash flow occur
NPV=-15000/(1+0%)^0+6630/(1+0%)^1+7971/(1+0%)^2+6730/(1+0%)^3
NPV=$6331
A project has the following cash flows: Year Cash Flows 0 -15000 1 6630 2 7971...
Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.97 million. The fixed asset will be depreciated straight-line to zero over its three-year tax life, after which time it will be worthless. The project is estimated to generate $2209946 in annual sales, with costs of $856923. If the tax rate is 37 percent and the required return on the project is 10 percent, what is the project's NPV? (Negative amount should be...
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $490,722 is estimated to result in some amount of annual pretax cost savings. The press will have an aftertax salvage value at the end of the project of $85,295. The OCFs of the project during the 4 years are $172,042, $198,396, $177,620 and $162,472, respectively. The press also requires an initial investment in spare parts inventory of $24,467, along with...
A project has the following cash flows: Year Cash Flow 0 –$ 16,300 1 7,000 2 8,300 3 6,800 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ ...
A) McGilla Golf has decided to sell a new line of golf clubs. The length of this project is seven years. The company has spent $104440 on research and development for the new clubs. The plant and equipment required will cost $2895663 and will be depreciated on a straight-line basis. The new clubs will also require an increase in net working capital of $130371 that will be returned at the end of the project. The OCF of the project will...
A project has the following cash flows Year Cash Flow 0 $17,400 8,100 9,400 7,900 2 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV What is the NPV at a discount rate of...
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $503,562 is estimated to result in $203,421 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $105,027. The shop's tax rate is 34 percent. What is the after-tax salvage value of this asset? (Round your final answer to the nearest dollar amount....
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $555,858 is estimated to result in $195,308 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $91,853. The shop's tax rate is 30 percent. What is the OCF for year 4? (Round your final answer to the nearest dollar amount. Omit the...
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $573,039 is estimated to result in $238,224 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $99,519. The shop's tax rate is 33 percent. What is the OCF for year 4? (Round your final answer to the nearest dollar amount. Omit the...
10.00 points A project has the following cash flows: Year 0 1 Cash Flow -$16,800 7,500 8,800 7,300 2 3 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the...
A) A project that provides annual cash flows of $14369 for eight years costs $77894 today. What is the NPV for the project if the required return is 7 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16)) B) A project that provides annual cash flows of $17545 for eight years costs $75634 today. What is the NPV for the project if the required return is 19 percent? (Negative amount...