Please help me fill those
in
and also what is Plan B's cost = ____$? (enter your response as a whole number)
We solve the given problem in POM-QM as shown below:
Regular time cost per unit = Labor cost per hour * Hours per refrigerator = 12 * 4 = $48
Overtime cost per unit = Overtime cost per hour * Hours per refrigerator = 18 * 4 = $72
Current production in December = No. of workers * Hours per day * Days per month / Hours per unit = 8 * 8 * 20 / 4 = 320 units
We enter the required data as shown below:
On solving, we get
The above solution in the table format as per question is:
Required answer in green.
Plan B's cost = $107200 as seen from middle table above
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!
Please help me fill those in and also what is Plan B's cost = ____$? (enter...
Need help filling the empty slots above in.
What is Plan A's cost = ___?(enter response as a whole
number)
Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following data: B Click the icon to view the company's data. Consider the two following strategies. a) Plan A: Vary the workforce so that production meets the forecasted demand (maintain inventory at 250 units). Bell had eight employees on staff in...
A disk drive manufacturer is in need of an aggregate plan for July to December. The company has gathered the following data: Month Demand Month Demand July 400 Oct 700 Aug 500 Nov 800 Sep 550 Dec 700 Item Cost Materials $35/disk Inventory $8/disk/month Subcontracting $80/disk Stock-out $15/disk Regular time labor $12/hour Overtime labor $18/hour (above 8 hrs) Hiring cost $40/worker Layoff cost $80/worker Other data include: Item Data Current workforce (June) 8 people Labor hours per disk 4 hrs...
Please help with the missing
numbers above
Also
Total hiring cost $ _?(enter response as whole number)
Total layoff cost $ _?(enter response as whole number)
Total inventory carrying cost $ _?(enter response as whole
number)
Total stockout cost $ _?(enter response as whole number)
Total cost, excluding normal time labor costs, for Plan B $
_?(enter response as whole number)
The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time...
USE LEVEL AGGREGATE PLAN: Cost data Regular time labor cost per hour $10 Overtime time labor cost per hour $15 Subcontracting cost per unit $80 Back order cost per unit per period $20 Inventory holding cost per unit per period $10 Hiring cost per employee $400 Firing cost per employee $500 Capacity data Beginning workforce 40 employees Beginning inventory 0 units Beginning backorders 0 units Production standard per unit (hours) 2 hours of labor per unit Regular time available per...
The total subcontracting
costequals=$ ????
(Enter your response as a whole number.)
Total cost with plan 5 = ????
Juarez has yet a sixth plan. A constant workforce of 7 is
selected, with the remainder of demand filled by subcontracting.
Evaluate this plan.The production rate per day equals= ????
A Juarez, Mexico, manufacturer of roofing supplies has developed monthly forecasts for a family of products. Data for the 6-month period January to June are presented in the table below. There...
Please answer only the empty boxes (bottom table and the
questions below it)
The total subtracting cost= $_______
The total inventory holding cost for January through August=
$_____
The total cost, excluding normal time labor costs, for Plan E=
$_____
Will thumps up if answers is correct!
The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 1,400 1,700 May 2,300 January February 2,300 June March 1,700 1,700 July April...
You are developing an aggregate plan for a toolbox maker which sells to professional mechanics. The relevant cost and demand data are shown below: Holding cost $8/toolbox/month Month Demand Subcontract $80/toolbox July 400 Regular time $45/toolbox August 500 OT Regular time cost plus additional $20 per toolbox September 500 Capacity increase $50/unit October 700 Capacity decrease $90/unit November 800 Backlog cost $10/toolbox/month December 700 June capacity and demand 500 toolboxes Beginning inventory 0 toolboxes Plan A: Try a level strategy...
Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The company has gathered the following data given in the tables. There are 8 hours of production per day. You manage a consulting firm down the street from Consuelo Chua, Inc., and to get your foot in the door, you have told Mr. Chua that you can do a better job at aggregate planning than his current staff. He said, "Fine. You...
a) the total cost of hiring=$ (enter your
response as a whole number)
b)the total cost of layoffs=$?(enter your response as a whole
number)
c)the total inventory carrying cost =$?(enter your response as a
whole number)
d)the total stockout cost$?(enter your response as a whole
number)
e) the total cost, excluding normal time labor cost, is =$
?(enter your response as a whole number)
The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next...
02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The com- pany has gathered the following data: COSTS Holding cost $8/disk/month Subcontracting 580/disk Regular-time labor $12 hour Overtime labor $18 hour for hours above 8 hours/workerday Hiring cost $4000/ worker Layoff cost $8000/worker DEMAND Note: In this problem (and Q3) the production cost should be computed based on the labor cost OTHER DATA Current worden 8 people Labor hours disk...