Question

A Juarez, Mexico, manufacturer of roofing supplies has developed monthly forecasts for a family of products. Data for the 6-mRegular Production Subcontract (Units) Month Demand 950 1 January 660 290 750 210 120 2 February 3 March 4 April 5 May 6 June

The total subcontracting

costequals=​$ ????

​(Enter your response as a whole​ number.)

Total cost with plan 5​ = ????

Juarez has yet a sixth plan. A constant workforce of 7 is​ selected, with the remainder of demand filled by subcontracting. Evaluate this plan.The production rate per day equals= ????

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Plan 5:

No. of constant workers to be maintained = 6 workers

Hours available per day per worker = 8 hours per day

Daily hours available per worker per day = 6*8 =48 hours

Labor hours per unit = 1.6 hours per unit = 1.6 hours per unit

Production rate per day = 56/1.6 = 30 units per day

Subcontract cost per unit = $ 10 per unit

Month

Production days

Demand Forecast

Regular Production

Subcontract (units)

Production cost

Subcontracting cost

Total cost

=30*Production days

=Demand Forecast - Regular Production

=Production days*$40*6 workers

=Subcontract units * Subcontract cost per unit

=Production cost + Subcontracting cost

January

22

950

660

290

5280

2900

8180

February

18

750

540

210

4320

2100

6420

March

21

750

630

120

5040

1200

6240

April

21

1000

630

370

5040

3700

8740

May

22

1300

660

640

5280

6400

11680

June

20

1050

600

450

4800

4500

9300

Total

29800

20800

50600

As per the above calculations:

Total Production cost = $ 29800

Total Subcontract cost = $ 20800

Total cost for plan 5= Total Production cost + Total Subcontracting cost = 29800+20800 = $50600

Plan 6:

No. of constant workers to be maintained = 7 workers

Hours available per day per worker = 8 hours per day

Daily hours available per worker per day = 7*8 = 56 hours

Labor hours per unit = 1.6 hours per unit = 1.6 hours per unit

Production rate per day = 56/1.6 = 35 units per day

Add a comment
Know the answer?
Add Answer to:
The total subcontracting costequals=​$ ???? ​(Enter your response as a whole​ number.) Total cost with plan...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please help with the missing numbers above Also Total hiring cost $ _?(enter response as whole...

    Please help with the missing numbers above Also Total hiring cost $ _?(enter response as whole number) Total layoff cost $ _?(enter response as whole number) Total inventory carrying cost $ _?(enter response as whole number) Total stockout cost $ _?(enter response as whole number) Total cost, excluding normal time labor costs, for Plan B $ _?(enter response as whole number) The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time...

  • a) the total cost of hiring=$ (enter your response as a whole number) b)the total cost...

    a) the total cost of hiring=$ (enter your response as a whole number) b)the total cost of layoffs=$?(enter your response as a whole number) c)the total inventory carrying cost =$?(enter your response as a whole number) d)the total stockout cost$?(enter your response as a whole number) e) the total cost, excluding normal time labor cost, is =$ ?(enter your response as a whole number) The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next...

  • Need help filling the empty slots above in. What is Plan A's cost = ___?(enter response...

    Need help filling the empty slots above in. What is Plan A's cost = ___?(enter response as a whole number) Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following data: B Click the icon to view the company's data. Consider the two following strategies. a) Plan A: Vary the workforce so that production meets the forecasted demand (maintain inventory at 250 units). Bell had eight employees on staff in...

  • Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The t...

    Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The total inventory holding cost for January through August= $_____ The total​ cost, excluding normal time labor​ costs, for Plan E= $_____ Will thumps up if answers is correct! The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 1,400 1,700 May 2,300 January February 2,300 June March 1,700 1,700 July April...

  • Please help me fill those in and also what is Plan B's cost = ____$? (enter...

    Please help me fill those in and also what is Plan B's cost = ____$? (enter your response as a whole number) Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following data: Click the icon to view the company's data. Consider the two following strategies. a) Plan A: Vary the workforce so that production meets the forecasted demand (maintain inventory at 250 units). Bell had eight employees on staff...

  • What are the numbers for subcontract (units) for the picture above? The total cost, excluding normal...

    What are the numbers for subcontract (units) for the picture above? The total cost, excluding normal time labor costs, for Plan A = $___?(enter response as a whole number) The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of $100 per unit, inventory carrying costs of $20 per unit per month, and zero beginning and ending inventory, evaluate these two plans on an incremental cost...

  • A disk drive manufacturer is in need of an aggregate plan for July to December. The...

    A disk drive manufacturer is in need of an aggregate plan for July to December. The company has gathered the following data: Month Demand Month Demand July 400 Oct 700 Aug 500 Nov 800 Sep 550 Dec 700 Item Cost Materials $35/disk Inventory $8/disk/month Subcontracting $80/disk Stock-out $15/disk Regular time labor $12/hour Overtime labor $18/hour (above 8 hrs) Hiring cost $40/worker Layoff cost $80/worker Other data include: Item Data Current workforce (June) 8 people Labor hours per disk 4 hrs...

  • The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sale per unit, inventory carrying costs of...

    The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sale per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate these two plans on an incremental cost basis: Plan A: Produce at a steady rate (equal to minimum requirements) of 1,100 units per month and subcontract additional units at a $60 per unit premium cost. Subcontracting capacity is...

  • Her operations manager is considering a new plan, which begins in January with 200 units on hand and ends with zero inv...

    Her operations manager is considering a new plan, which begins in January with 200 units on hand and ends with zero inventory. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan B. Plan B: Produce at a constant rate of 1,400 units per month, which will meet minimum demands. Then use subcontracting, with additional units at a premium price of $75 per...

  • 02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for...

    02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The com- pany has gathered the following data: COSTS Holding cost $8/disk/month Subcontracting 580/disk Regular-time labor $12 hour Overtime labor $18 hour for hours above 8 hours/workerday Hiring cost $4000/ worker Layoff cost $8000/worker DEMAND Note: In this problem (and Q3) the production cost should be computed based on the labor cost OTHER DATA Current worden 8 people Labor hours disk...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT