Daily usage of bailing wire is 900 feet
Lead time is 6 workdays
Service level is given as 98% ( 1.00-0.98 = 0.02)
For 0.02, safety stock is given as 1800 feet
Reorder point:
Reorder point = (Demand * Leadtime) + Safety stock
= 900*6 + 1800
= 7200 feet
Hence the reorder point is 7200 feet.
A newspaper publisher uses roughly 900 feet of baling wire each day to secure bundles of...
A newspaper publisher uses roughly 890 feet of baling wire each day to secure bundles of newspapers while they are being distributed to carriers. The paper is published Monday through Saturday. Lead time is 5 workdays. What is the appropriate reorder point quantity, given that the company desires a service level of 95 percent, if that stockout risk for various levels of safety stock is as follows: 1,500 feet, 10; 1,700 feet, .05 1,800 feet, .02; and 2,800 feet, .01?...