On July 31, 2017, Amsterdam Company engaged Minsk Tooling Company to construct a special- purpose piece...
On July 31, 2017, Amsterdam Company engaged Minsk Tooling Company to construct a special- purpose piece of factory machinery. Construction was begun immediately and was completed on November 30, 2017. To help finance construction, on July 31 Amsterdam issued a $80,000, 3 year, 11% notes payable, on which interest is payable each July 31. In addition, the company had outstanding all year a 8%, 3-year, $100,000 note payable and an 10%, 4-year, $150,000 note payable. Interests on both 8% and...
On July 31, 2017, Tamarisk Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction was begun immediately and was completed on November 1, 2017. To help finance construction, on July 31 Tamarisk issued a $296,400, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $190,400 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in short-term...
On July 31, 2017, Whispering Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction was begun immediately and was completed on November 1, 2017. To help finance construction, on July 31 Whispering issued a $301,200, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $195,200 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in short-term...
On July 31, 2017, Concord Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery, Construction was begun immediately and was completed on November 1, 2017. To help finance construction, on July 31 Concord issued a $303,600, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $196,600 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in short-term...
On July 31, 2020, Sarasota Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction begun immediately and was completed on November 1, 2020. To help finance construction, on July 31 Sarasota issued a $270,000, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $175,000 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in short-term marketable...
On July 31, 2020, Whispering Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction begun immediately and was completed on November 1, 2020. To help finance construction, on July 31 Whispering issued a $320,400, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $211,400 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in short-term marketable...
On July 31, 2020, Ivanhoe Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction begun immediately and was completed on November 1, 2020. To help finance construction, on July 31 Ivanhoe issued a $303,600, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $196,600 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in short-term marketable...
On July 31, 2020, Cheyenne Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction begun immediately and was completed on November 1, 2020. To help finance construction, on July 31 Cheyenne issued a $303,600, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $208,600 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in short-term marketable...
Question 5 On July 31, 2020, Cullumber Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction begun immediately and was completed on November 1, 2020. To help finance construction, on July 31 Cullumber issued a $326,400, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $217,400 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in...
Exercise 10-09 On July 31, 2020, Shamrock Company engaged Minsk Tooling Company to construct a special-purpose piece of factory machinery. Construction begun immediately and was completed on November 1, 2020. To help finance construction, on July 31 Shamrock issued a $283,200, 3-year, 12% note payable at Netherlands National Bank, on which interest is payable each July 31. $175,200 of the proceeds of the note was paid to Minsk on July 31. The remainder of the proceeds was temporarily invested in...