Question 2a: [10marks] An off-grid solar PV system installed for Mr Effah Ransford consist of a...
..11 TELUS 10:24 AM 53%. , Done Design an OFF-GRID PV System in the range of 3-SKW Max two udents per project Your project should contain the following sections: 1) Summary of your PV system providing the size, location, solar window, PV Watts 2) AC/DC Load Calculations- Need to be belevable, allow provision for a 1/2hp sump pump and a minimum of SOOW DC loading ) Detailed drawing showing major components including manufacturers cut sheets with Sizing calculations for PW...
(c) Photovoltaic system installed to supply 2 kWh of energy per day pumping system which using centrifugal pump and DC motor. The peak sun hours in Oman are 6 h and the expected Project Life (PL) is 24 years. The system is designed to have the components and rating is as shown in Table Q3c1. Table Q3c2 shows the actual costs, quantities and life periods of the various components that are considered for Life Cycle Cost (LCC) calculations. Assume the...