Question
I will rate

2. A process has a X-bar control chart with UCL-17.4. LCL-12.79 using a 3-sigma limit. The subgroup sample size is 3. (a) Est
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER:

0 Given details, UCL 174 LCL = 12-11 / Sample size in): 3 (subgroup) a. from the control chart table (2) for n=3, A2=1.023 ,4.4 2 -0.21 22 L -PL 1-331) 1-331). -P[-0.273<225.73) $15.73) – iⓇ (-0.273) -0.99 - (0.5-P[0<220-273]] (due to symmetric natu

Add a comment
Know the answer?
Add Answer to:
I will rate 2. A process has a X-bar control chart with UCL-17.4. LCL-12.79 using a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. A process has a X-bar control chart with UCL=17.4, LCL=12.79 using a 3- sigma limit....

    2. A process has a X-bar control chart with UCL=17.4, LCL=12.79 using a 3- sigma limit. The subgroup sample size is 3. (a) Estimate the standard deviation of the process, sigma hat. (6 pts) (b) Suppose that the process mean shifts to 13. Find the probability that this shift will be detected on the next sample. (8 pts) (c) Calculate the average run length (ARL) before detecting the shift. (6 pts)

  • Control charts for bar x chart and S have been maintained on a process and have...

    Control charts for bar x chart and S have been maintained on a process and have exhibited statistical control. The sample size is n=6. The control chart parameters are as follows: Estimate the mean and standard deviation of the process. Assume that the process output is well modeled by a normal distribution. If specifications are 703 and 709, estimate the fraction nonconforming. Suppose the process mean shifts to 702.00 while the standard deviation remains constant. What is the probability of...

  • 1. Design X-bar and R charts a control chart with "standards given" as an aimed-at mean...

    1. Design X-bar and R charts a control chart with "standards given" as an aimed-at mean of Xo 4.0, Sigma 0033, and Subgroup size 5. It is not necessary to sketch the control-chart since we have no points to put on it. Just specify, CL, UCL and LCL. That is the design. 2. Then find the probability of in-control nonconformance given, USL 4.00995 and LSL = 3.99005 3. Also, by theory, what is the Probability of an out-of-control point when...

  • Given the following measurements representing 10 samples of size 3. find the s-bar, UCL and LCL...

    Given the following measurements representing 10 samples of size 3. find the s-bar, UCL and LCL for a S-bar chart. Is the process in control 2 3 4 5 6 7 8 9 | 10A 10 5 10 8 9 88 892 | 102 103 104 105 101 103N00EUBU 9.94 0.9 103 10.8 || 10 H104 10. 610103 0 19.79 10 3 102 s-bar 027 UCL 0.68 LCL 0 1 The process is in control s-bar 0.27 UCL 0.65 LCLLO...

  • Consider the p chart below. Note that LCL 0, CLp0.01667, and UCL 0.04802 Does the process...

    Consider the p chart below. Note that LCL 0, CLp0.01667, and UCL 0.04802 Does the process appear to be in a state of statistical control? a. P Chartof Nonconforming Units 0.05 UaL-0.04802 b. What sample size is needed in order to have a positive lower 0.04 control limit? E 0.03 0.02 ?-0.0 1667 0.01 0.00 1 3 5 79111315 17 19

  • Design X-bar and R charts a control chart with "standards given" as an aimed-at mean of...

    Design X-bar and R charts a control chart with "standards given" as an aimed-at mean of Xo = 4.0, Sigma = .0033, and Subgroup size = 5. It is not necessary to sketch the control-chart since we have no points to put on it. Just specify, CL, UCL and LCL. That is the design. Then find the probability of in-control nonconformance given, USL = 4.00995 and LSL = 3.99005 Also, by theory, what is the Probability of an out-of-control point...

  • I will rate 1. For constructing a X-bar chart, subgroup sample average (x bar) and range(r)...

    I will rate 1. For constructing a X-bar chart, subgroup sample average (x bar) and range(r) are computed for each of 24 preliminary samples using a sample size n=5. 24 24 We have the following data summary: Ex-816 and r - 113 Il El (a) Find the following for X-bar chart:(6 pts) Upper control limit, Center line, and Lower controllimit (b) Find the following for R chart: (6 pts) Upper controllimit, Center line, and Lower controllimit: (c) Calculate the fraction...

  • 1. Design X-bar and R charts a control chart with "standards given" as an aimed-at mean...

    1. Design X-bar and R charts a control chart with "standards given" as an aimed-at mean of Xo = 4.0, Sigma = .0033, and Subgroup size -5. It is not necessary to sketch the control-chart since we have no points to put on it. Just specify, CL, UCL and LCL. That is the design. 2. Then find the probability of in-control nonconformance given, USL = 4.00995 and LSL 3.99005 3. Also, by theory, what is the Probability of an out-of-control...

  • 1. Design X-bar and R charts a control chart with "standards given" as an aimed-at mean...

    1. Design X-bar and R charts a control chart with "standards given" as an aimed-at mean of Xo = 4.0, Sigma = .0033, and Subgroup size -5. It is not necessary to sketch the control-chart since we have no points to put on it. Just specify, CL, UCL and LCL. That is the design. 2. Then find the probability of in-control nonconformance given, USL = 4.00995 and LSL 3.99005 3. Also, by theory, what is the Probability of an out-of-control...

  • A) Set the control limits for the process for the x(bar) chart when the maching is working proper...

    round to 3 decimal places ? A) Set the control limits for the process for the x(bar) chart when the maching is working properly UCL-x-? grams (round to two decimal places) LCL-x grams (round to two decimal places) B) Set the control limits for this process for the R-chart. UCLrgrams (round to two decimal places) LCLr grams (round to two decimal places) Refer to the table Factors for Computing Control Chart Limits (3 sigma) for this problem. Your supervisor, Lisa...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT