For Level plan,
Add up the total demand = 500 + 800 + 1,000 + 1,400 + 2,000 +
3,000 + 2,700 + 1,500 + 1,400 + 1,500 + 2,000 + 1,200
Total Demand for 12 months = 19,000 units
Average Demand for month = 19,000 / 12 = 1,583.33 units
It is given that a single worker can produce 10 units per month,
that implies for producing 1,583 units we need
1,583.33/10 = 158 employees (or) if you want to round off up front
we may need 159 employees
For Chase Plan,
The total demand for the month is as it is taken up for production and we calculate individual number of workers required for the respective months. So for,
Month 1 = Demand = 500 ; Number of workers = 500/10 = 50
Month 2 = Demand = 800 ; Number of workers = 800/10 = 80
Month 3 = Demand = 1,000 ; Number of workers = 1,000/10 = 100
Month 4 = Demand = 1,400 ; Number of workers = ,400/10 = 140
Month 5 = Demand = 2,000 ; Number of workers = 2,000/10 = 200
Month 6 = Demand = 3,000 ; Number of workers = 3,000/10 = 300
Month 7 = Demand = 2,700 ; Number of workers = 2,700/10 = 270
Month 8 = Demand = 1,500 ; Number of workers = 1,500/10 = 150
Month 9 = Demand = 1,400 ; Number of workers = 1,400/10 = 140
Month 10 = Demand = 1,500 ; Number of workers = 1,500/10 =
150
Month 11 = Demand = 2,000 ; Number of workers = 2,000/10 =
200
Month 12 = Demand = 1,200 ; Number of workers = 1,200/10 = 120
Mixed strategy Production Plan
Mixed Strategy | ||||||||||||
Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Demand | 500 | 800 | 1000 | 1400 | 2000 | 3000 | 2700 | 1500 | 1400 | 1500 | 2000 | 1200 |
Beginning inventory | 0 | 1130 | 1960 | 2590 | 2820 | 2450 | 1080 | 10 | 0 | 0 | 0 | 0 |
Production required | 500 | -330 | -960 | -1190 | -820 | 550 | 1620 | 1490 | 1400 | 1500 | 2000 | 1200 |
Regular workforce | 163 | 163 | 163 | 163 | 163 | 163 | 163 | 149 | 140 | 150 | 200 | 120 |
Regular production | 1630 | 1630 | 1630 | 1630 | 1630 | 1630 | 1630 | 1490 | 1400 | 1500 | 2000 | 1200 |
Ending inventory | 1130 | 1960 | 2590 | 2820 | 2450 | 1080 | 10 | 0 | 0 | 0 | 0 | 0 |
Workers hired | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 10 | 50 | 0 |
Workers fired | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 14 | 9 | 0 | 0 | 80 |
Cost: | ||||||||||||
Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Production cost per worker ($2000/month) | $326,000 | $326,000 | $326,000 | $326,000 | $326,000 | $326,000 | $326,000 | $298,000 | $280,000 | $300,000 | $400,000 | $240,000 |
Inventory holding cost ($32/unit/month) | $36,160 | $62,720 | $82,880 | $90,240 | $78,400 | $34,560 | $320 | $0 | $0 | $0 | $0 | $0 |
Hiring cost ($2000 per worker) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $20,000 | $100,000 | $0 |
Firing cost ($500 per worker) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $7,000 | $4,500 | $0 | $0 | $40,000 |
Total monthly cost | $362,160 | $388,720 | $408,880 | $416,240 | $404,400 | $360,560 | $326,320 | $305,000 | $284,500 | $320,000 | $500,000 | $280,000 |
Total cost | $4,356,780 |
Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): Month 1...
How do I calculate the one time adjustment of workforce to support the level production plan? Problem information: Month: 1 2 3 4 5 6 7 8 9 10 11 12 Demand: 500 800 1000 1400 2000 3000 2700 1500 1400 1500 2000 1200 Management at the Kerby Corporation has determined the following aggregated demand schedule in Units. An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular time wages...
Find a level workforce plan that relies just on overtime and the minimum amount of undertime possible. Overtime can be used to its limits in any quarter. What is the total cost of the plan? $954200 (Enter your response as an integer.) How many undertime hours does it call for? 21500 hours. (Enter your response as an integer.) b. Use a chase strategy that varies the workforce level without using overtime or undertime. What is the total cost of this...
The Barberton Municipal division of Road Maintenance is charged with road repair in the city of Barberton and the surrounding area. Cindy Kramer, road maintenance director, must submit a staffing plan for the next year based on a set schedule for repairs and on the city budget. Kramer estimates that the labor hours required for the next four quarters are 7,000, 13,000, 19,000, and 10,000, respectively. Each of the 11 workers on the workforce can contribute 500 hours per quarter....
Each certified instructor puts in 480 hours per quarter regular time and can work an additional 120 hours overtime. Regular-time wages and benefits cost Carlton $7,200 per employee per quarter for regular time worked up to 480 hours, with an overtime cost of $20 per hour. Unused regular time for certified instructors is paid at $15 per hour. There is no cost for unused overtime capacity The cost of hiring, training, and certifying a new employee is $10,000. Layoff costs...
Bob Carlton's golf camp estimates the following workforce requirements for its services over the next two years: Quarter 1 2 3 4 5 6 7 8 Demand (hrs) 4,400 6,500 3,200 5,200 4,500 6,300 3,800 4,900 Each certified instructor puts in 480 hours per quarter regular time and can work an additional 120 hours overtime. Regular-time wages and benefits cost Carlton $7,200 per employee per quarter for regular time worked up to 480 hours, with an overtime cost of $20...
Andree’s All-American manufactures fashionable tennis wear, needs help planning production for next year. Demand for tennis gear is fairly stable, but has peaks during the summer months. Month Demand Forecast January 500 February 300 March 200 April 1500 May 2500 June 3500 July 4500 August 2500 September 500 October 300 November 300 December 2500 Beginning workforce 9 workers Production per day 9 units per employee Production cost during regular time $50 per unit Subcontracting cost $75 per unit Increasing production...
Her operations manager is considering a new plan, which begins in January with 200 units on hand and ends with zero inventory. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan B. Plan B: Produce at a constant rate of 1,400 units per month, which will meet minimum demands. Then use subcontracting, with additional units at a premium price of $75 per...
Nowjuice, Inc., produces bottled pomegranate juice. A planner has developed an aggregate forecast for demand for the next six months. Month May Jun jul Aug Sep oct Forecast 4000 4800 5600 7200 6400 5000 Use the following information to develop aggregate plans. Regular production cost $ 10 per case Regular production capacity 5000 cases Overtime production cost $ 16 per case Subcontracting cost $ 20 per case Inventory cost $ 1 per case per month Beginning inventory 0 Develop...
Climate Control, Inc. makes expedition-quality rain gear for outdoor enthusiasts. Management prepared a forecast of sales (in suits) for next year and now must prepare a production plan. The company has traditionally maintained a level workforce strategy. All nine workers are treated like family and have been employed by the company for a number of years. Each employee can produce 2,000 suits per month. At present, finished goods inventory holds 24,000 suits. The demand forecast follows: a. Management is willing...
#8 7. Suppose that Sam's Cat Hotel in the problem above uses a P system instead of a system. The average daily demand is d = 96/6 = 16 bags, and the standard deviation of daily demand is 0, od = 16 = To = 6.142 bags "week_15 a. What P (in working days) and T should be used to approximate the cost trade-offs of the EOQ? b. How much more safety stock is needed with a P system than...