A) Staffing plan based on level strategy is following:

B C D E F G HIJK N O SSolver Parameters 1 Level strategy CostCategory cate 2 Quarter 3 Demand (hours 4 Regular time 5 Overtim

EXCEL FORMULAS:

Cell Formula Copy to
C6 =C3-SUM(C4:C5) C6:J6
C7 =480*C9-C4 C7:J7
C8 =120*C9-C5 C8:J8
C9 =B9+C10-C11 C9:J9
K3 =SUM(C3:J3) K3:K11
M5 =K5*L5 M5:M11
M14 =SUM(M3:M11)

B) Staffing plan based on Chase strategy is following:

B C D E FG HIJK N O 1 Chase strategy 2 Quarter S Solver Parameters Cost/Category 8 Total SMS14 3 Demand (hours 4 Regular time

C) Better plan based on Mixed strategy is following:

B C D EF G HIJK 1Mixed strategy CostCategory SSolver Parameters 2 Quarter 8 Total 4200 6400 3000 4800 440062403600480037440 4

Add a comment
Know the answer?
Add Answer to:
Each certified instructor puts in 480 hours per quarter regular time and can work an additional 1...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Bob Carlton's golf camp estimates the following workforce requirements for its services over the next two...

    Bob Carlton's golf camp estimates the following workforce requirements for its services over the next two years: Quarter 1 2 3 4 5 6 7 8 Demand (hrs) 4,400 6,500 3,200 5,200 4,500 6,300 3,800 4,900 Each certified instructor puts in 480 hours per quarter regular time and can work an additional 120 hours overtime. Regular-time wages and benefits cost Carlton $7,200 per employee per quarter for regular time worked up to 480 hours, with an overtime cost of $20...

  • Tim Booker's tennis camp estimates the workforce requirements for its services over the next two years...

    Tim Booker's tennis camp estimates the workforce requirements for its services over the next two years in the accompanying table. Quarter 1 2 3 4 5 6 7 8 Demand(hours) 4,200 6,400 3,000 4,800 4,400 6,240 3,600 4,800 Each certified instructor puts in 480 hours per quarter regular time and can work an additional 120 hours overtime.​ Regular-time wages and benefits cost Booker $ 7,200 per employee per quarter for regular time worked up to 480 hours, with an overtime...

  • #8 7. Suppose that Sam's Cat Hotel in the problem above uses a P system instead...

    #8 7. Suppose that Sam's Cat Hotel in the problem above uses a P system instead of a system. The average daily demand is d = 96/6 = 16 bags, and the standard deviation of daily demand is 0, od = 16 = To = 6.142 bags "week_15 a. What P (in working days) and T should be used to approximate the cost trade-offs of the EOQ? b. How much more safety stock is needed with a P system than...

  • The Barberton Municipal division of Road Maintenance is charged with road repair in the city of...

    The Barberton Municipal division of Road Maintenance is charged with road repair in the city of Barberton and the surrounding area. Cindy​ Kramer, road maintenance​ director, must submit a staffing plan for the next year based on a set schedule for repairs and on the city budget. Kramer estimates that the labor hours required for the next four quarters are 7,000​, 13,000​, 19,000​, and 10,000​, respectively. Each of the 11 workers on the workforce can contribute 500 hours per quarter....

  • The Barberton Municipal division of Road Maintenance is charged with road repair in the city of B...

    The Barberton Municipal division of Road Maintenance is charged with road repair in the city of Barberton and the sumounding area. Cindy Kramer, road maintenance director, must submit a staffing plan for Kramer estimates that the labor hours required for the next four quarters are 6,000, 12.000. 20,000, and 9.000 the 11 workers on the workforce can contribute 500 hours per quarter. Payroll costs are $6,000 in wages per worker for regular time worked up to 500 hours, with an...

  • Find a level workforce plan that relies just on overtime and the minimum amount of undertime...

    Find a level workforce plan that relies just on overtime and the minimum amount of undertime possible. Overtime can be used to its limits in any quarter. What is the total cost of the​ plan? ​$954200 ​(Enter your response as an​ integer.) How many undertime hours does it call​ for? 21500 hours. ​(Enter your response as an​ integer.) b. Use a chase strategy that varies the workforce level without using overtime or undertime. What is the total cost of this​...

  • USE LEVEL AGGREGATE PLAN: Cost data Regular time labor cost per hour $10 Overtime time labor...

    USE LEVEL AGGREGATE PLAN: Cost data Regular time labor cost per hour $10 Overtime time labor cost per hour $15 Subcontracting cost per unit $80 Back order cost per unit per period                           $20 Inventory holding cost per unit per period           $10 Hiring cost per employee $400 Firing cost per employee $500 Capacity data Beginning workforce                                                             40 employees Beginning inventory 0 units Beginning backorders 0 units Production standard per unit (hours)                       2 hours of labor per unit Regular time available per...

  • 02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for...

    02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The com- pany has gathered the following data: COSTS Holding cost $8/disk/month Subcontracting 580/disk Regular-time labor $12 hour Overtime labor $18 hour for hours above 8 hours/workerday Hiring cost $4000/ worker Layoff cost $8000/worker DEMAND Note: In this problem (and Q3) the production cost should be computed based on the labor cost OTHER DATA Current worden 8 people Labor hours disk...

  • Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000;...

    Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000; winter, 18,800. At the beginning of spring, you have 66 workers and 990 units in inventory. The union contract specifies that you may lay off workers only once a year, at the beginning of summer. Also, you may hire new workers only at the end of summer to begin regular work in the fall. The number of workers laid off at the beginning of...

  • Develop a production plan and calculate the annual cost for a firm whose demand forecast is...

    Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT