Question

Develop a production plan and calculate the annual cost for a firm whose demand forecast is...

Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on overtime during winter or spring only if overtime is necessary to prevent stockouts at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, $90 for each temp; layoff, $180 for each worker laid off; inventory holding, $5 per unit-quarter; backorder, $10 per unit; straight time, $5 per hour; overtime, $8 per hour. Assume that the productivity is 0.5 unit per worker hour, with eight hours per day and 60 days per season. In each quarter, produce to the full output of your regular workforce, even if that results in excess production. In Winter and Spring, use overtime only if needed to meet the production required in that quarter. Do not use overtime to build excess inventory in prior seasons expressly for the purpose of reducing the number of temp workers in Summer. (Leave no cells blank - be certain to enter "0" wherever required. Negative values should be indicated by a minus sign. Round up "Number of temp workers, Workers hired and Workers laid off" to the next whole number and all other answers to the nearest whole number.)

Fall Winter Spring Summer
Forecast 11,000 7,700 6,700 13,000
Beginning inventory
Production required
Production hours required
Production hours available
Overtime hours
Temp workers
Temp worker hours available
Total hours available
Actual production
Ending inventory
Workers hired
Workers laid off
Fall Winter Spring Summer
Straight time
Overtime
Inventory
Backorder
Hiring
Layoff
Total
Annual cost
1 0
Add a comment Improve this question Transcribed image text
Answer #1

A B C D E F 1 N 3 4 5 6 7 00 9 10 11 12 13 Fall Winter Spring Summer Forecast 11000 7700 6700 13000 Beginning inventory 550 =

Fall Winter Spring Summer
Forecast 11,000 7,700 6,700 13,000
Beginning inventory 550 -3,250 0 500
Production required 10,450 10,950 6,700 12,500
Production hours required 20,900 21,900 13,400 25,000
Production hours available 14,400 14,400 14,400 14,400
Overtime hours 0 7,500 0 0
Temp workers 0 0 0 23
Temp worker hours available 0 0 0 11,040
Total hours available 14,400 21,900 14,400 25,440
Actual production 7,200 10,950 7,200 12,720
Ending inventory -3,250 0 500 220
Workers hired 0 0 0 23
Workers laid off 0 0 0 23
Qtr-1 Qtr-2 Qtr-3 Qtr-4
Straight time $72,000 $72,000 $72,000 $127,200
Overtime $0 $60,000 $0 $0
Inventory $0 $0 $2,500 $1,100
Backorder $32,500 $0 $0 $0
Hiring $0 $0 $0 $2,070
Layoff $0 $0 $0 $4,140
Total $104,500 $132,000 $74,500 $134,510
Annual cost $445,510
Add a comment
Know the answer?
Add Answer to:
Develop a production plan and calculate the annual cost for a firm whose demand forecast is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand...

    Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,700; winter, 8,300; spring, 6,900; summer, 12,700. Inventory at the beginning of fall is 535 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular...

  • Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000;...

    Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000; winter, 18,800. At the beginning of spring, you have 66 workers and 990 units in inventory. The union contract specifies that you may lay off workers only once a year, at the beginning of summer. Also, you may hire new workers only at the end of summer to begin regular work in the fall. The number of workers laid off at the beginning of...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Problem 8-8 Plan production for a four-month period: February through May. For February and March, you...

    Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...

  • Develop a production schedule to produce the exact production requirements by varying the workforce size for...

    Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem The monthly forecasts for Product X for January February, and March 1010, 1510 and 1180 respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 530 units Manufacturing cost is $180 por unit, storage cost is...

  • Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the...

    Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. The monthly forecasts for Product X for January, February, and March are 1,010, 1,540, and 1,180, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February and 21 in March. Beginning inventory is 530 units. Manufacturing cost is $180 per...

  • Q. Find optimal solution Demand & # of working days Jan Feb Mar Ap May Jun Total Forecast 2.760 3...

    How can i solve optimalsolution?? Q. Find optimal solution Demand & # of working days Jan Feb Mar Ap May Jun Total Forecast 2.760 3.320 3,970 3,540 3,180 2,900 19,670 # of working days: 21 20 23 21 4 units/worker/day inventory holding cost is $2 per gear per month. oHiring cost: $200 per worker Layoff cost: $500 per worker Wages and benefits: $15/worker/hour 8 hours/ day, 35 workers Beginning workforce level1437 Beginning inventory level -215000 Ending inventory level 5 days...

  • A disk drive manufacturer is in need of an aggregate plan for July to December. The...

    A disk drive manufacturer is in need of an aggregate plan for July to December. The company has gathered the following data: Month Demand Month Demand July 400 Oct 700 Aug 500 Nov 800 Sep 550 Dec 700 Item Cost Materials $35/disk Inventory $8/disk/month Subcontracting $80/disk Stock-out $15/disk Regular time labor $12/hour Overtime labor $18/hour (above 8 hrs) Hiring cost $40/worker Layoff cost $80/worker Other data include: Item Data Current workforce (June) 8 people Labor hours per disk 4 hrs...

  • Problem 2 D small manufacturing company is manufact has prring company is planing production requirements requ...

    Problem 2 D small manufacturing company is manufact has prring company is planing production requirements requ ected demand bplanning production requirements for next year. The Sales by quarter as shown below: Winter Average quarterly demand 3500 units 3800 units 4200 units 4500 units Suppose the company had 50 workers and 1.600 units in inventory at the beginning of the winter The company wishes to finish the year with an inventory of 1,000 units on hand. The average pay per worker...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT