Question

Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the workforce size
January February March Labor Inventory Hiring Layoff Total Total
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Production schedule based on varying workforce strategy is as follows:

A B C January 22 D February 19 March 21 Working days 1,180 590 775 995 42 119 60 56 14 0 59 1008 603 4 Forecast 1,010 1,540 5

EXCEL FORMULAS:

January February March
Working days 22 19 21
Forecast 1010 1540 1180
Safety Stock =C4/2 =D4/2 =E4/2
Beginning inventory =B12 =C12 =D12
Net production required =C4+C5-C6 =D4+D5-D6 =E4+E5-E6
Workers required 42 =ROUNDUP(C7/0.1/C2/8,0) =ROUNDUP(D7/0.1/D2/8,0) =ROUNDUP(E7/0.1/E2/8,0)
Hired =MAX(0,C8-B8) =MAX(0,D8-C8) =MAX(0,E8-D8)
Laid off =MAX(0,B8-C8) =MAX(0,C8-D8) =MAX(0,D8-E8)
Actual production =ROUND(C2*C8*8*0.1,0) =ROUND(D2*D8*8*0.1,0) =ROUND(E2*E8*8*0.1,0)
Ending inventory 530 =-C4+C6+C11 =-D4+D6+D11 =-E4+E6+E11
January February March
Labor 6 =C2*C8*8*$B15 =D2*D8*8*$B15 =E2*E8*8*$B15
Inventory 6 =C12*$B16 =D12*$B16 =E12*$B16
Hiring 210 =C9*$B17 =D9*$B17 =E9*$B17
Layoff 310 =C10*$B18 =D10*$B18 =E10*$B18
Total cost for the month =SUM(C15:C18) =SUM(D15:D18) =SUM(E15:E18)
Total Cost of the plan (excluding manufacturing cost)    =SUM(C19:E19)
Add a comment
Know the answer?
Add Answer to:
Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Develop a production schedule to produce the exact production requirements by varying the workforce size for...

    Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem The monthly forecasts for Product X for January February, and March 1010, 1510 and 1180 respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 530 units Manufacturing cost is $180 por unit, storage cost is...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Problem 8-8 Plan production for a four-month period: February through May. For February and March, you...

    Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...

  • AGGREGATE PLANNING Garden Hub makes a single product, a garden tool that sells for $40. Garden Hub starts with 1000 of these tools in inventory and is expected to end with at least 500 in stock. Garde...

    AGGREGATE PLANNING Garden Hub makes a single product, a garden tool that sells for $40. Garden Hub starts with 1000 of these tools in inventory and is expected to end with at least 500 in stock. Garden Hub can temporarily backlog demand for a cost, but at the end of the time horizon, they require their backlog to be zero – This is an important constraint to remember- if we forget it, we will get strange results . Production costs...

  • Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand...

    Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,700; winter, 8,300; spring, 6,900; summer, 12,700. Inventory at the beginning of fall is 535 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular...

  • Develop a production plan and calculate the annual cost for a firm whose demand forecast is...

    Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...

  • Complete the level production plan, using the following information. The only costs you need to consider...

    Complete the level production plan, using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plan correctly, your hiring, layoff, and inventory costs should match those given here. E: Click the icon to view the costs table. Click the icon to view the forecasted sales. Fill in the production plan table below (enter your responses rounded to the nearest whole number). Month Forecasted sales Sales in worker hours...

  • Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next...

    Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next six months MonthMay June July Aug Sept Oct Demand 260 240 240 240 270 290 The firm always plans to meet all demand. The firm currently has 260 workers capable of producing 260 units in a month (1 unit/worker). The workforce can be increased (at a cost of $650 (at a cost of $1,300 per worker). Inventory holding cost is $150 per unit per...

  • Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000;...

    Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000; winter, 18,800. At the beginning of spring, you have 66 workers and 990 units in inventory. The union contract specifies that you may lay off workers only once a year, at the beginning of summer. Also, you may hire new workers only at the end of summer to begin regular work in the fall. The number of workers laid off at the beginning of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT