Question

A construction company has an expenditure rate of ​E(x)=e^0.13x dollars per day on a particular paving...

A construction company has an expenditure rate of

​E(x)=e^0.13x

dollars per day on a particular paving job and an income rate of

​I(x)=124.1−e^0.13x

dollars per day on the same​ job, where x is the number of days from the start of the job. The​ company's profit on that job will equal total income less total expenditures. Profit will be maximized if the job ends at the optimum​ time, which is the point where the two curves meet.

​(a) Find the optimum number of days for the job to last.

​(b) Find the total income for the optimum number of days.

​(c) Find the total expenditures for the optimum number of days.

​(d) Find the maximum profit for the job.

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Ang Given that, 0.13 X E(x) = se I (W) - 0.13% 14.1-e (a) Nowo, Ecx) I(x) 0.137 0.13 X 124.1-e 0.13 x 1241 0.13% 124.1 2 0,13I 112 ) + (39401175-24.1975 )-( 0.13 ( 3940.175-477.097479 ) +7.6923 3463.078 +7.6923 3470.77 Z Il 31.75 (0) Total expenditur

Add a comment
Know the answer?
Add Answer to:
A construction company has an expenditure rate of ​E(x)=e^0.13x dollars per day on a particular paving...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company has found that its rate of expenditure (in hundreds of dollars) on a certain...

    A company has found that its rate of expenditure (in hundreds of dollars) on a certain type of job is given by E'(x) = 2x+4, where x is the number of days since the start of the job. Find the total expenditure if the job takes 5 days. O A. $45 OB. $4,500 O c. $14 OD. $1,400 4 2 where t is measured in hours after the drug is administered. Find the total reaction For a certain drug, the...

  • A company determines that its marginal revenue per day is given by R'(t), where R(t) is...

    A company determines that its marginal revenue per day is given by R'(t), where R(t) is the total accumulated revenue, in dollars, on the tth day. The company's marginal cost per day is given by C' (t), where C(t) is the total accumulated cost, in dollars, on the th day. R' (t) = 140 e'. R(O)=0; C' (t) = 140 -0.75, C(O) = 0 a) Find the total profit P(T) from t=0 to t= 10 (the first 10 days). P(T)...

  • QUESTION 2 10 marks A construction company pays its temporary workers R100 per day if they...

    QUESTION 2 10 marks A construction company pays its temporary workers R100 per day if they work on a Monday to Saturday and R200 if they work on a Sunday. They only work when the company contacts them, so they do not work the whole month. Complete the program below that asks the user to enter the days that the worker has worked. The character '1' is entered if the day is Monday to Saturday and '2' if it is...

  • A construction company pays its temporary workers R100 per day if they work on a Monday...

    A construction company pays its temporary workers R100 per day if they work on a Monday to Saturday and R200 if they work on a Sunday. They only work when the company contacts them, so they do not work the whole month. Complete the program below that asks the user to enter the days that the worker has worked. The character 'l' is entered if the day is Monday to Saturday and '2' if it is a Sunday. A total...

  • A construction company pays its temporary workers R100 per day if they work on a Monday...

    A construction company pays its temporary workers R100 per day if they work on a Monday to Saturday and R200 if they work on a Sunday. They only work when the company contacts them, so they do not work the whole month. Complete the program below that asks the user to enter the days that the worker has worked. The character 'l' is entered if the day is Monday to Saturday and 2’ if it is a Sunday. A total...

  • QUESTION 2 10 marks A construction company pays its temporary workers R100 per day if they...

    QUESTION 2 10 marks A construction company pays its temporary workers R100 per day if they work on a Monday to Saturday and R200 if they work on a Sunday. They only work when the company contacts them, so they do not work the whole month. Complete the program below that asks the user to enter the days that the worker has worked. The character 'l' is entered if the day is Monday to Saturday and '2' if it is...

  • QUESTION 2 10 marks A construction company pays its temporary workers R100 per day if they...

    QUESTION 2 10 marks A construction company pays its temporary workers R100 per day if they work on a Monday to Saturday and R200 if they work on a Sunday. They only work when the company contacts them, so they do not work the whole month. Complete the program below that asks the user to enter the days that the worker has worked. The character 'l'is entered if the day is Monday to Saturday and 2' if it is a...

  • A chemical substance has a decay rate of 745 per day. The rate of change of...

    A chemical substance has a decay rate of 745 per day. The rate of change of an amount of the chemical is given by the equation -0074N where is the number of days since decay began. Complete parts a) through c) a) Let No represent the amount of the chemical substance att. Find the exponential function that models the situation N) – Ng. b) Suppose that 400 g of the chemical substance is present att0 How much will remain after...

  • (1 point) A company finds that the rate at which the quantity of a product that...

    (1 point) A company finds that the rate at which the quantity of a product that consumers demand changes with respect to price is given by the marginal-demand function D'(x) = -2000 where x is the price per unit, in dollars. Find the demand function if it is known that 105 units of the product are demanded by consumers when the price is 20 dollars per unit. Demand function D(x) = (1 point) Find the area under the curve 2x-1...

  • 1000 3d +11 bicycles per day after d days of on-the-job training. A company that makes...

    1000 3d +11 bicycles per day after d days of on-the-job training. A company that makes bicycles has determined that a new employee can assemble M(d), where Md) a. Find the rate of change function for the number of bicycles assembled with respect to time. b. Find and interpret M' (2) and M'(5). The rate of change function for the number of bicycles assembled with respect to time is M'(d)=0

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT