Question

Problem 1 (10 credits) A lake has an area of 10 km². During a specific month the lake evaporation was 90 mm. During the same


please my teachers

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2-28 1 X10 mg no Imonth= (60x60x24 X30) seconds a) AQ = in flow- out flow = 1.2-1-1=001 m/s 0.1 x660X 60X 24x30) m?/month in

sir,hope this helped u

sir,please give a rating

Add a comment
Know the answer?
Add Answer to:
please my teachers Problem 1 (10 credits) A lake has an area of 10 km². During...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A lake with a drainage area AD has a surface area of AL and an average...

    A lake with a drainage area AD has a surface area of AL and an average depth of zL. The long-term rates of precipitation and evapotranspiration for the portion of the drainage basin are PD and eD, respectively. For the lake itself the average rate of precipitation and evaporation are PL and eL, respectively. Average rate of stream outflow is Q. There is no groundwater inflow or outflow to the basin. a. Identify the units (Length[L], Time [T], Mass [M],...

  • sovle it in understandable line please. thank you. Question 2- Surface area of a lake is...

    sovle it in understandable line please. thank you. Question 2- Surface area of a lake is 400 km' and annual precipitation is 32.5 cm. Inflow rate of stream is 2.54 m/s and outflow rate of stream is 2.67 m/s. Water surface level in the lake is increased by 22 mm during the year. Neglect the infiltration in the lake and compute the evaporation height in the lake for the related year.

  • Subject: Water Resource Engineering 9. A lake has a surface area of 850,000 m 2. For...

    Subject: Water Resource Engineering 9. A lake has a surface area of 850,000 m 2. For a given month (30 days), the lake has an inflow of 1.7 m23/s and an outflow of 1.3mA3/s. The water level in the lake was raised by 1.0 m. The total precipitation for the month is 23 cm. Assume that seepage loss is negligible. Determine the evaporation loss (in cm) for the lake

  • ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site...

    ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site on Gediz River in June 1971. Find the monthly evaporation in mm from the reservoir surface of this dam. If there were a Class A pan installed nearby the reservoir, what would be the monthly evaporation observed from this pan? Storage at the beginning of the month : 4XY.Z - 10 m Storage at the end of the month 47x V -10 m Average...

  • ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site...

    ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site on Gediz River in June 1971. Find the monthly evaporation in mm from the reservoir surface of this dam. If there were a Class A pan installed nearby the reservoir, what would be the monthly evaporation observed from this pan? Storage at the beginning of the month : 4XY.Z - 10 m Storage at the end of the month 47x V -10 m Average...

  • ENGINEERING HYDROLOGY CIVL431 Assignment1 Problem 11 The following data were observed at Demirkopru Dam site on...

    ENGINEERING HYDROLOGY CIVL431 Assignment1 Problem 11 The following data were observed at Demirkopru Dam site on Gedir River in June 1971. Find the monthly evaporation in mm from the reservoir surface of this dam. If there were a Class A pan installed nearby the reservoir, what would be the monthly evaporation observed from this pan? Storage at the beginning of the month 4XY.X-10 m Storage at the end of the month 47XY -10 m Average surface area of reservoir in...

  • ENCE 3327 13/2 lake with an 18-km' surface area has an inflow of 10 m's from several streams with...

    ENCE 3327 13/2 lake with an 18-km' surface area has an inflow of 10 m's from several streams with an average phosphorus (P) concentration of 0.02 mg/L. A municipal wastewater plant discharges its treated cfluent to the lake at 0.05 m/s with a P concentration of 10 mg/L. Assuming the P settling rate is 5 cm/d, determine. ath state concentration in the lake, and b) the P % removal necessary in the incomin a P steady-state concentration in the lake...

  • During the month of March, the average river inflow to a reservoir is 3 m’/s while...

    During the month of March, the average river inflow to a reservoir is 3 m’/s while the dam bottom outlet releases 10 m²/s. Total rainfall for the month is measured as 20 mm uniformly distributed. The average seepage from the reservoir is estimated 0.5 m3/s. The surface areas of the lake are measured from aerial photos as 11.7 and 10.3 km2 and also the staff gauge readings of water surface are recorded as 107.2 m and 105.2 m in the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT