Question

ENGINEERING HYDROLOGY CIVL431 Assignment1 Problem 11 The following data were observed at Demirkopru Dam site on Gedir River i
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Problem 1

Storage at beginning of month S1= 439.5*106 m3

Storage at the end of month S2= 453.9*106 m3

Change in storage \Delta S = S2 - S1 = 453.9*106 -439.5*106 = 14.4*106 m3

Mean inflow = 13.3 m3/s

Inflow volume for the month of June,1971 , I = 13.3*30*24*60*60 = 34.47*106 m3

Amount of water used for power production = Op = 49.5*106 m3

Average seepage rate in the month = 595.53 l/s

Seepage volume for the month Os= 595.53*10-3*30*24*60*60 = 1.54*106 m3

Precipitation P = 0

Using water budget equation ,

P + I = Op + Os + \Delta S +E​​​​​​L

0 + 34.47*106 = 49.5*106 + 1.54*106 + 14.4 * 106 + EL

EL = -30.97*106 ​​​​ m3

Depth of evaporation = EL/ Surface area = -30.97*106 /33.9*106 = -0.91 m

Evaporation cannot be negative. So evaporation is taken as zero.

Pan evaporation = Lake evaporation/ pan coefficient

Pan coefficient taken as 0.7 usually

Problem 2

Surface area = 0.97x Actual Surface area = 0.97*33.9 = 32.883 km2

Mean inflow = 13.3 m3/s

Inflow volume I = 13.3*31*24*60*60 = 35.62*106 m3

Op = 49.5 m3

Os = 595.53 *10-3*31*24*60*60 = 1.595 *106 m3

EL = 0

P + I = Op + Os + \Delta S + EL

35.62*106 = 49.5*106 + 1.595*106 + \Delta S

\DeltaS = -15.475*106 m3

Decline in water level = 15.475*106/32.883*106 = 0.47 m =47 cm

Problem 3

Precipitation P= 395 mm

Evapotranspiration ET = 95 mm

Infiltration I = 15 mm

Area A = 395 km2

Assuming no other losses,

Runoff R = Precipitation (P) - Evapotranspiration (ET) - Infiltration (I)

= P - ET - I = 395 - 95 - 15 = 285 mm

Runoff depth = 285 mm = 0.285 m

Runoff volume = Runoff depth *Area = 0.285*395*106 = 112.575*106 m3

There are 30 days in the month of June. So,

Rate of runoff = Runoff volume/ Duration = 112.575*106 / (30*24*60*60) = 43.432 m3/s = 43432 lt/s

Problem 4

Precipitation = 15 mm

Area of catchment = 73 km2

Area of lake = 5.3 km2

Area contributing to surface runoff = 73 - 5.3 = 67.7 km2

Total Infiltration depth = 9 mm

Runoff depth = Precipitation- Losses = Precipitation- Infiltration = 15-9 = 6 mm

Volume of surface runoff = Runoff depth * Area contributing to surface runoff = 6*10-3 * 67.7 *106 = 406200 m3

Problem 5

Surface area of lake = 79 ha

Inflow rate = 0.395 m3/s

Inflow volume = 0.395*30*24*60*60 = 1.024*106 m3

Outflow rate = 593 lt/s = 0.593 m3/s

Outflow volume = 0.593*30*24*60*60 = 1.537*106 m3

Precipitation = 33.5 mm

Precipitation volume = 33.5*10-3*790000 = 0.0265 * 106 m3

Change in storage \Delta s = -539500 m3

P + I = O + \Delta S + E

E = P + I - O - \Delta S = 0.0265*106 + 1.024*106 - 1.537*106 + 0.5395*106

E = 0.053*106 m3

Evaporation depth = Evaporation/ Surface area = 0.053*106 / 790000 = 0.067 m = 67 mm

Add a comment
Know the answer?
Add Answer to:
ENGINEERING HYDROLOGY CIVL431 Assignment1 Problem 11 The following data were observed at Demirkopru Dam site on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site...

    ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site on Gediz River in June 1971. Find the monthly evaporation in mm from the reservoir surface of this dam. If there were a Class A pan installed nearby the reservoir, what would be the monthly evaporation observed from this pan? Storage at the beginning of the month : 4XY.Z - 10 m Storage at the end of the month 47x V -10 m Average...

  • ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site...

    ENGINEERING HYDROLOGY CIVL431 Assignment #1 Problem 11 The following data were observed at Demirköprü Dam site on Gediz River in June 1971. Find the monthly evaporation in mm from the reservoir surface of this dam. If there were a Class A pan installed nearby the reservoir, what would be the monthly evaporation observed from this pan? Storage at the beginning of the month : 4XY.Z - 10 m Storage at the end of the month 47x V -10 m Average...

  • Q2) (8 Marks) A) Estimate the constant rate of withdrawal (in m's) from a 13.75 km...

    Q2) (8 Marks) A) Estimate the constant rate of withdrawal (in m's) from a 13.75 km reservoir in a month of 30 days during which the reservoir level dropped by 0.75 m in spite of an average inflow into the reservoir of 0.5 Mm /day. During the month the average seepage loss from the reservoir was 2.5 cm, total precipitation on the reservoir was 18.5 cm and the total evaporation was 9.5 cm B) If the surface area of a...

  • During the month of March, the average river inflow to a reservoir is 3 m’/s while...

    During the month of March, the average river inflow to a reservoir is 3 m’/s while the dam bottom outlet releases 10 m²/s. Total rainfall for the month is measured as 20 mm uniformly distributed. The average seepage from the reservoir is estimated 0.5 m3/s. The surface areas of the lake are measured from aerial photos as 11.7 and 10.3 km2 and also the staff gauge readings of water surface are recorded as 107.2 m and 105.2 m in the...

  • 3. Compute a weekly evaporation rate (in mm/week) from the surface water reservoir applying the following...

    3. Compute a weekly evaporation rate (in mm/week) from the surface water reservoir applying the following recorded data: average inflow into water reservoir = 32.5 m3/s, average outflow from reservoir = 40.2 m3/s, average rainfall during the week = 73.6 mm, surface water reservoir area = 15.8 km², estimated total water infiltration or seepage out during the week from this reservoir = 0.25 million m”, reservoir storage at the beginning of week = 9180 ha-m (hectare-meter), reservoir storage at the...

  • Course: Engineering Hydrology Problem 3.11. The isohyetal map of a basin for an 18 hr storm...

    Course: Engineering Hydrology Problem 3.11. The isohyetal map of a basin for an 18 hr storm is given in Figure 3.36. Determine the areal mean precipitation and the depth-area curve for this storm. 25 mm 30 mm bin 17 km) 20 mm 5 km217 22 km2 15 mm 31 km2 27 km2 10 mm 18 km2 5 mm 4 km2

  • Determine the minimum surface area in acres of an irrigation reservoir so that the drawdown over...

    Determine the minimum surface area in acres of an irrigation reservoir so that the drawdown over August is no more than 10 ft. the drainage basin feeding into the reservoir, including the reservoir itself, is 100 mi 2. Assume that 35% of the rain falling on the basin runs off the reservoir. Assume groundwater flow into and out of the basin is negligible. Determine the irrigation water needed from the evapotranspiration requirement from beans growing on 40mi 2 at 35...

  • A lake with a drainage area AD has a surface area of AL and an average...

    A lake with a drainage area AD has a surface area of AL and an average depth of zL. The long-term rates of precipitation and evapotranspiration for the portion of the drainage basin are PD and eD, respectively. For the lake itself the average rate of precipitation and evaporation are PL and eL, respectively. Average rate of stream outflow is Q. There is no groundwater inflow or outflow to the basin. a. Identify the units (Length[L], Time [T], Mass [M],...

  • Problem 2 ENVL GEOL 3435 | Spring 2019 At a water elevation of 6391 ft, Mono...

    Problem 2 ENVL GEOL 3435 | Spring 2019 At a water elevation of 6391 ft, Mono Lake has a volume of 2,939,000 ac-ft, and a surface area of 48,10o ac. Annual inputs to the lake include 8 in. of direct precipitation, runoff fróm gauged streams of 150,000 ac-ft per year, and ungauged runoff and groundwater inflow of 37,000 ac-ft per year. Evaporation is 49 in. per year. Atotal of 85,000 ac-ft of wate rise or fall? Provide evidence for your...

  • please my teachers Problem 1 (10 credits) A lake has an area of 10 km². During...

    please my teachers Problem 1 (10 credits) A lake has an area of 10 km². During a specific month the lake evaporation was 90 mm. During the same month the inflow to the lake from a river was on average 1.2 m/s and the outflow from the lake via another river was on average 1.1 m/s. Also, for the same month a water level increase of 100 mm for the lake was observed. a) What was the precipitation in mm...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT