Question

The reason is the NPV and IRR approaches use different reinvestment rate assumptions so there can be a conflict in project ac

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :

NPV and IRR approaches use different reinvestment rate assumptions and
so there can be a conflict in project acceptance when mutually exclusive projects are considered.
Reinvestment at the WACC is the superior assumption,
so when mutually exclusive projects are evaluated the NPV approach should be used for the capital budgeting decision.

Thumbs up please

Add a comment
Know the answer?
Add Answer to:
The reason is the NPV and IRR approaches use different reinvestment rate assumptions so there can...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound...

    Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is: CFt is the expected cash flow in Period t and cash outflows are treated...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 2 3 4 Project A...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 2 3 4 Project A...

  • call U Lise Blueprint Problems Ch 11 Brigham Quantitative Problem: Bellinger Industries is considering two projects...

    call U Lise Blueprint Problems Ch 11 Brigham Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all Included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is...

  • Please answer a through d Same question Quantitative Problem: Bellinger Industries is considering two projects for...

    Please answer a through d Same question Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%....

  • X Blueprint Problems Ch 11 Brigham 0 Quantitative Problem: Bellinger Industries is considering two projects for...

    X Blueprint Problems Ch 11 Brigham 0 Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 12%....

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to de the analysis. Both projects after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%. 1. Project A -1,100 600 360 270...

  • First Blank: always, sometimes, never Second Blank: IRR, MIRR, required rate of return Third Blank: IRR,...

    First Blank: always, sometimes, never Second Blank: IRR, MIRR, required rate of return Third Blank: IRR, MIRR, required rate of return Fourth Blank: IRR method, NPV method 6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree....

  • Dropdown options first 2 blanks: (internal rate of return IRR, required rate of return, modified internal...

    Dropdown options first 2 blanks: (internal rate of return IRR, required rate of return, modified internal rate of return MIRR) Dropdown options 3rd blank: (NPV method, IRR method) If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. always Projects Y and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT