Question

Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound...

Capital Budgeting Decision Criteria: IRR

IRR
A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is:

CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal -Select-IRRonezeroCorrect 3 of Item 1.

The IRR calculation assumes that cash flows are reinvested at the -Select-IRRNPVWACCCorrect 4 of Item 1. If the IRR is -Select-lessgreaterCorrect 5 of Item 1 than the project's cost of capital, then the project should be accepted; however, if the IRR is less than the project's cost of capital, then the project should be -Select-acceptedrejectedCorrect 6 of Item 1. Because of the IRR reinvestment rate assumption, when -Select-mutually exclusiveindependent companyCorrect 7 of Item 1 projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR: -Select-returntimingpreferenceCorrect 8 of Item 1 differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the -Select-IRRNPVeitherCorrect 9 of Item 1 method should be used to evaluate projects.

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%.

0 1 2 3 4
Project A -1,050 610 385 290 330
Project B -1,050 210 320 440 780

What is Project A’s IRR? Round your answer to two decimal places.

%

What is Project B's IRR? Round your answer to two decimal places.

%

If the projects were independent, which project(s) would be accepted according to the IRR method?

-Select-NeitherProject AProject BBoth Projects A and BCorrect 1 of Item 3

If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method?

-Select-Neither Project AProject BBoth Projects A and BCorrect 2 of Item 3

Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive?

-Select-YesNoCorrect 3 of Item 3

The reason is -Select-the NPV and IRR approaches use the same reinvestment rate assumption so both approaches reach the same project acceptance when mutually projects are considered.the NPV and IRR approaches use different reinvestment rate assumptions so there can be a conflict in project acceptance when mutually exclusive projects are considered.Correct 4 of Item 3

Reinvestment at the -Select-IRRWACCCorrect 5 of Item 3 is the superior assumption, so when mutually exclusive projects are evaluated the -Select-NPVIRRCorrect 6 of Item 3 approach should be used for the capital budgeting decision.

  • Check My Work
1 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer Part 1:

A project's internal rate of return (IRR) is the discount rate that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the YTM on a bond. The equation for calculating the IRR is:

CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal zero.

The IRR calculation assumes that cash flows are reinvested at the IRR. If the IRR is greater than the project's cost of capital, then the project should be accepted; however, if the IRR is less than the project's cost of capital, then the project should be -rejected. Because of the IRR reinvestment rate assumption, when mutually exclusive projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR: timing differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the NPV method should be used to evaluate projects.

Answer Part 2:

(a) Project A’s IRR = 23.03%

(b) Project B’s IRR =19.10%

(c) If the projects were independent then according to the IRR method:

Both Projects would be accepted since IRRs of both projects are higher than WACC.

(d) If the projects were mutually exclusive then according to the IRR method:

Project A would be accepted a, since it has higher IRR.

(e) Yes, there could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive

As we observe above, Project B has higher NPV but Poject A has higher IRR.

As HOMEWORKLIB's policy 4 parts need to be answered. I have already answered more than 4 parts.

Add a comment
Know the answer?
Add Answer to:
Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 2 3 4 Project A...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 2 3 4 Project A...

  • IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate...

    IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-on a bond. The equation for calculating the IRR is: ;that forces the PV of its inflows to equal its cost. CF2 CFN 1 IRF 1 IRF 1IR CFt t-1 (1 +IRR) CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must...

  • СР, 0 A project's internal rate of return (IRR) is the -Select- that forces the PV...

    СР, 0 A project's internal rate of return (IRR) is the -Select- that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rat of return, and it is comparable to the - Select on a bond. The equation for calculating the IRR is: NPV = CF. + CF + СР + ... + =0 (1 + IRR) (1 + ru (1 + R) CF (1 + IRR) CFt is the expected...

  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been...

    Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%. 0 1 2 3 4 Project A -970 670...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 2 3 4 Project A...

  • The reason is the NPV and IRR approaches use different reinvestment rate assumptions so there can...

    The reason is the NPV and IRR approaches use different reinvestment rate assumptions so there can be a conflict in project acceptance when mutually exclusive projects are considered. v approach should be used for the Reinvestment at the WACC is the superior assumption, so when mutually exclusive projects are evaluated the NPV capital budgeting decision.

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 0 1 2 3 4 Project A...

  • Dropdown options first 2 blanks: (internal rate of return IRR, required rate of return, modified internal...

    Dropdown options first 2 blanks: (internal rate of return IRR, required rate of return, modified internal rate of return MIRR) Dropdown options 3rd blank: (NPV method, IRR method) If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. always Projects Y and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT